Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets
- Item number
- 9.47.1
- Analysis basis
- 2m long
- Priced inputs
- 7
- Derived rate
- ₹175.00/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.47.1 (Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets : 20 mm dia (heavy type)) is derived from 7 priced inputs for 2m long and works out to ₹175.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7034 | MAT | Nickle plated M.S. pipe 20 mm dia.Nickel plated M.S. pipe 20 mm dia | metre | 2 | 78.00 | 156.00 |
| 7035 | MAT | Nickle plated M.S. Brackets for curtain rod 20 mmNickel plated M.S. Brackets for curtain rod 20 mm | each | 2 | 7.00 | 14.00 |
| 9999 | MAT | Screws | L.S. | 4.03 | 2.27 | 9.15 |
| 9999 | MAT | CARRIAGE | L.S. | 1.56 | 2.27 | 3.54 |
| 7048 | MAT | Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10) | each | 2 | 24.00 | 48.00 |
| 9999 | MAT | Labour including fixing rawl plug | L.S. | 5.2 | 2.27 | 11.80 |
| 9999 | MAT | Sundries | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 246.03
- Add 1 % Water charges on “W”
- +2.46
- TOTAL
- 248.49
- Add GST on “X” (multiplying factor 0.2127)
- +52.85
- TOTAL
- 301.34
- Add 15% CPOH on “Y”
- +45.20
- TOTAL
- 346.54
- Add Cess @ 1% on “Z”
- +3.47
- Cost for 2 metre
- 350.01
- Cost of 1 metre
- 175.01
- SAY
- ₹175.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 501
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 501. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.