Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets

20 mm dia (heavy type)
Item number
9.47.1
Analysis basis
2m long
Priced inputs
7
Derived rate
₹175.00/ METRE
D-01/RATE ANALYSISITEM 9.47.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.47.1 (Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets : 20 mm dia (heavy type)) is derived from 7 priced inputs for 2m long and works out to ₹175.00 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.47.1DETAILS OF COST FOR 2M LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7034MATNickle plated M.S. pipe 20 mm dia.Nickel plated M.S. pipe 20 mm diametre278.00156.00
7035MATNickle plated M.S. Brackets for curtain rod 20 mmNickel plated M.S. Brackets for curtain rod 20 mmeach27.0014.00
9999MATScrewsL.S.4.032.279.15
9999MATCARRIAGEL.S.1.562.273.54
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each224.0048.00
9999MATLabour including fixing rawl plugL.S.5.22.2711.80
9999MATSundriesL.S.1.562.273.54
BUILD-UP TO RATE
TOTAL
246.03
Add 1 % Water charges on “W”
+2.46
TOTAL
248.49
Add GST on “X” (multiplying factor 0.2127)
+52.85
TOTAL
301.34
Add 15% CPOH on “Y”
+45.20
TOTAL
346.54
Add Cess @ 1% on “Z”
+3.47
Cost for 2 metre
350.01
Cost of 1 metre
175.01
SAY
₹175.00
D-02/SOURCEPRINTED PAGE 501
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
501

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 501. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.