Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets
- Item number
- 9.47.2
- Analysis basis
- 2m long
- Priced inputs
- 7
- Derived rate
- ₹186.40/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.47.2 (Providing and fixing nickel plated M.S. pipe curtain rods with nickel plated brackets : 25 mm dia (heavy type)) is derived from 7 priced inputs for 2m long and works out to ₹186.40 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7033 | MAT | Nickel plated M.S. pipe 25mm diaNickel plated M.S. pipe 25 mm dia | metre | 2 | 84.00 | 168.00 |
| 7036 | MAT | Nickle plated M.S. Brackets for curtain rod 25 mmNickel plated M.S - Brackets for curtain rod 25 mm | each | 2 | 9.00 | 18.00 |
| 9999 | MAT | Screws | L.S. | 4.03 | 2.27 | 9.15 |
| 9999 | MAT | CARRIAGE | L.S. | 1.56 | 2.27 | 3.54 |
| 7048 | MAT | Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10) | each | 2 | 24.00 | 48.00 |
| 9999 | MAT | Labour including fixing rawl plug | L.S. | 5.2 | 2.27 | 11.80 |
| 9999 | MAT | Sundries | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 262.03
- Add 1 % Water charges on “W”
- +2.62
- TOTAL
- 264.65
- Add GST on “X” (multiplying factor 0.2127)
- +56.29
- TOTAL
- 320.94
- Add 15% CPOH on “Y”
- +48.14
- TOTAL
- 369.08
- Add Cess @ 1% on “Z”
- +3.69
- Cost for 2 metre
- 372.77
- Cost of 1 metre
- 186.39
- SAY
- ₹186.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 501
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 501. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.