Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete
- Item number
- 9.46.3
- Analysis basis
- 2m long
- Priced inputs
- 7
- Derived rate
- ₹525.55/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.46.3 (Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete : 25 mm dia) is derived from 7 priced inputs for 2m long and works out to ₹525.55 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0592 | MAT | Chromium plated Brass curtain rod 25 mm dia 1.25mm thickChromium plated Brass curtain rod 25 mm dia 1.25 mm thick | metre | 2 | 347.00 | 694.00 |
| 7023 | MAT | Chromium plated brackets ( curtain rods)Chromium plated brackets (curtain rods) | each | 2 | 9.00 | 18.00 |
| 9999 | MAT | C.P. brass screws | L.S. | 4.03 | 2.27 | 9.15 |
| 9977 | MAT | CARRIAGE | L.S. | 1.56 | 2.27 | 3.54 |
| 0458 | MAT | PVC cleeves for screwsplastic sleeves for screw | each | 2 | 2.20 | 4.40 |
| 9999 | MAT | LABOUR | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | MAT | Sundries | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 738.83
- Add 1 % Water charges on “W”
- +7.39
- TOTAL
- 746.22
- Add GST on “X” (multiplying factor 0.2127)
- +158.72
- TOTAL
- 904.94
- Add 15% CPOH on “Y”
- +135.74
- TOTAL
- 1,040.68
- Add Cess @ 1% on “Z”
- +10.41
- Cost for 2 metre
- 1,051.09
- Cost of 1 metre
- 525.55
- SAY
- ₹525.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 500
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 500. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.