CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete

20 mm dia

Item number
9.46.2
Analysis basis
Details of cost for 2m long
Priced inputs
7
Derived rate
393.25 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.46.2 Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete : 20 mm dia — is derived from 7 priced inputs for 2m long and works out to ₹393.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0591Chromium plated Brass curtain rod 20 mm dia 1.25mm thickChromium plated Brass curtain rod 20 mm dia 1.25 mm thickMaterialmetre2254.00508.00
7023Chromium plated brackets ( curtain rods)Chromium plated brackets (curtain rods)Materialeach29.0018.00
9999C.P. brass screwsMaterialL.S.4.032.279.15
9977CARRIAGEMaterialL.S.1.562.273.54
0458PVC cleeves for screwsplastic sleeves for screwMaterialeach22.204.40
9999LABOURMaterialL.S.2.732.276.20
9999SundriesMaterialL.S.1.562.273.54
TOTAL
552.83
Add 1 % Water charges on “W”
5.53
TOTAL
558.36
Add GST on “X” (multiplying factor 0.2127)
118.76
TOTAL
677.12
Add 15% CPOH on “Y”
101.57
TOTAL
778.69
Add Cess @ 1% on “Z”
7.79
Cost for 2 metre
786.48
Cost of 1 metre
393.24
Say
393.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 499. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works