Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete

20 mm dia
Item number
9.46.2
Analysis basis
2m long
Priced inputs
7
Derived rate
₹393.25/ METRE
D-01/RATE ANALYSISITEM 9.46.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.46.2 (Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete : 20 mm dia) is derived from 7 priced inputs for 2m long and works out to ₹393.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.46.2DETAILS OF COST FOR 2M LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0591MATChromium plated Brass curtain rod 20 mm dia 1.25mm thickChromium plated Brass curtain rod 20 mm dia 1.25 mm thickmetre2254.00508.00
7023MATChromium plated brackets ( curtain rods)Chromium plated brackets (curtain rods)each29.0018.00
9999MATC.P. brass screwsL.S.4.032.279.15
9977MATCARRIAGEL.S.1.562.273.54
0458MATPVC cleeves for screwsplastic sleeves for screweach22.204.40
9999MATLABOURL.S.2.732.276.20
9999MATSundriesL.S.1.562.273.54
BUILD-UP TO RATE
TOTAL
552.83
Add 1 % Water charges on “W”
+5.53
TOTAL
558.36
Add GST on “X” (multiplying factor 0.2127)
+118.76
TOTAL
677.12
Add 15% CPOH on “Y”
+101.57
TOTAL
778.69
Add Cess @ 1% on “Z”
+7.79
Cost for 2 metre
786.48
Cost of 1 metre
393.24
SAY
₹393.25
D-02/SOURCEPRINTED PAGE 499
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
499

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 499. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.