CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete
12 mm dia
- Item number
- 9.46.1
- Analysis basis
- Details of cost for 2m long
- Priced inputs
- 7
- Derived rate
- ₹285.10 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.46.1 — Providing and fixing chromium plated brass curtain rod having wall thickness of 1.25mm with two chromium plated brass brackets fixed with C.P. brass screws and PVC sleeves etc., wherever necessary complete : 12 mm dia — is derived from 7 priced inputs for 2m long and works out to ₹285.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0590 | Chromium plated Brass curtain rod 12 mm dia 1.25mm thickChromium plated Brass curtain rod 12 mm dia 1.25 mm thickMaterial | metre | 2 | 178.00 | 356.00 |
| 7023 | Chromium plated brackets ( curtain rods)Chromium plated brackets (curtain rods)Material | each | 2 | 9.00 | 18.00 |
| 9999 | C.P. brass screwsMaterial | L.S. | 4.03 | 2.27 | 9.15 |
| 9977 | CARRIAGEMaterial | L.S. | 1.56 | 2.27 | 3.54 |
| 0458 | PVC cleeves for screwsplastic sleeves for screwMaterial | each | 2 | 2.20 | 4.40 |
| 9999 | LABOURMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 9999 | SundriesMaterial | L.S. | 1.56 | 2.27 | 3.54 |
- TOTAL
- 400.83
- Add 1 % Water charges on “W”
- 4.01
- TOTAL
- 404.84
- Add GST on “X” (multiplying factor 0.2127)
- 86.11
- TOTAL
- 490.95
- Add 15% CPOH on “Y”
- 73.64
- TOTAL
- 564.59
- Add Cess @ 1% on “Z”
- 5.65
- Cost for 2 metre
- 570.24
- Cost of 1 metre
- 285.12
- Say
- 285.10
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 499. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.