Extra for using veneered particle board conforming to IS 3097 Grade I, in item of pelmet 18mm thick 150mm wide

Non decorative veneer on both sides
Item number
9.44.1
Analysis basis
a pelmet
Priced inputs
1
Derived rate
₹38.70/ METRE
D-01/RATE ANALYSISITEM 9.44.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.44.1 (Extra for using veneered particle board conforming to IS 3097 Grade I, in item of pelmet 18mm thick 150mm wide Non decorative veneer on both sides) is derived from 1 priced inputs for a pelmet and works out to ₹38.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) 18mm thick particle board (medium density
  • exterior grade)
  • Front-1x1.7x0.15= 0.255sqm.+
  • Sides-2x0.15x0.15= 0.045sqm.
  • Total = 0.300sqm.+
  • Total = 0.315sqm. Say 0.32 sqm.
  • Add wastage @5% = 0.015sqm.
ANALYSIS OF RATES · ITEM 9.44.1DETAILS OF COST FOR A PELMET 2M LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0347MATExtra for veneered particle board with Commercial veneering on both sidessqm0.32170.0054.40
BUILD-UP TO RATE
TOTAL
54.40
Add 1 % Water charges on “W”
+0.54
TOTAL
54.94
Add GST on “X” (multiplying factor 0.2127)
+11.69
TOTAL
66.63
Add 15% CPOH on “Y”
+9.99
TOTAL
76.62
Add Cess @ 1% on “Z”
+0.77
Cost of 2m
77.39
Cost of 1 metre
38.70
SAY
₹38.70
D-02/SOURCEPRINTED PAGE 497
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
497

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 497. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.