CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete

Item number
9.43
Analysis basis
Details of cost for a pelmet 2m long
Priced inputs
12
Derived rate
725.85 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.43 Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete — is derived from 12 priced inputs for a pelmet and works out to ₹725.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • (i) 18mm thick Coir veneered board
  • Front-1x1.7x0.15= 0.255sqm.+
  • Sides-2x0.15x0.15= 0.045sqm.
  • Total = 0.300sqm.+
  • Total = 0.315sqm. Say 0.32 sqm.
  • 6mm thick commercial ply wood
  • Top-1x1.7x0.15= 0.255sqm.+
  • Total = 0.268 sqm. Say 0.27 sqm.
  • Add wastage @5% = 0.015sqm.
  • Add wastage @ 5% = 0.013 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
7556Coir veneered board 18mm thickCoir veneered board 18 mm thickMaterialsqm0.32980.00313.60
7553Coir veneered board 6mm thickCoir veneered board 6 mm thickMaterialsqm0.27368.0099.36
7034Nickle plated M.S. pipe 20 mm dia.Nickel plated M.S. pipe 20 mm diaMaterialmetre1.6578.00128.70
7035Nickle plated M.S. Brackets for curtain rod 20 mmNickel plated M.S. Brackets for curtain rod 20 mmMaterialeach27.0014.00
9977Carriage of materialMaterialL.S.0.522.271.18
9999M.S. flat 25x3mm and 10cm long over bracketsMaterialL.S.8.062.2718.30
2505Hollock wood in planksMaterial10 cudm0.032409.0013.09
7048Rawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)Materialeach224.0048.00
0112Carpenter 2nd classLabourday0.18816.00146.88
0114BeldarLabourday0.18736.00132.48
0130MistryLabourday0.11897.0098.67
9999SundriesMaterialL.S.2.732.276.20
TOTAL
1,020.46
Add 1 % Water charges on “W”
10.20
TOTAL
1,030.66
Add GST on “X” (multiplying factor 0.2127)
219.22
TOTAL
1,249.88
Add 15% CPOH on “Y”
187.48
TOTAL
1,437.36
Add Cess @ 1% on “Z”
14.37
Cost of 2 m
1,451.73
Cost of 1 metre
725.87
Say
725.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 497. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.