Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete

Item number
9.43
Analysis basis
a pelmet
Priced inputs
12
Derived rate
₹725.85/ METRE
D-01/RATE ANALYSISITEM 9.43

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.43 (Providing and fixing 18 mm thick, 150 mm wide pelmet of coir veneer board ISI marked IS : 14842, including top cover of 6 mm coir veneer board, nickle plated M.S. Pipe 20 mm dia. (heavy type) curtain rod with nickel plated brackets, including fixing with 25x3 mm M.S. Flat 10 cm long fixed to pelmet with hollock wood cleats of size 100 mm x 40 mm x 40 mm on both inner side of pelmet and rawl plugs 75 mm long etc. all complete) is derived from 12 priced inputs for a pelmet and works out to ₹725.85 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) 18mm thick Coir veneered board
  • Front-1x1.7x0.15= 0.255sqm.+
  • Sides-2x0.15x0.15= 0.045sqm.
  • Total = 0.300sqm.+
  • Total = 0.315sqm. Say 0.32 sqm.
  • 6mm thick commercial ply wood
  • Top-1x1.7x0.15= 0.255sqm.+
  • Total = 0.268 sqm. Say 0.27 sqm.
  • Add wastage @5% = 0.015sqm.
  • Add wastage @ 5% = 0.013 sqm.
ANALYSIS OF RATES · ITEM 9.43DETAILS OF COST FOR A PELMET 2M LONG
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7556MATCoir veneered board 18mm thickCoir veneered board 18 mm thicksqm0.32980.00313.60
7553MATCoir veneered board 6mm thickCoir veneered board 6 mm thicksqm0.27368.0099.36
7034MATNickle plated M.S. pipe 20 mm dia.Nickel plated M.S. pipe 20 mm diametre1.6578.00128.70
7035MATNickle plated M.S. Brackets for curtain rod 20 mmNickel plated M.S. Brackets for curtain rod 20 mmeach27.0014.00
9977MATCarriage of materialL.S.0.522.271.18
9999MATM.S. flat 25x3mm and 10cm long over bracketsL.S.8.062.2718.30
2505MATHollock wood in planks10 cudm0.032409.0013.09
7048MATRawl plug 50 mm (designation 10 no.)Rawl plug 50 mm (designation 10)each224.0048.00
0112LABCarpenter 2nd classday0.18816.00146.88
0114LABBeldarday0.18736.00132.48
0130LABMistryday0.11897.0098.67
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
1,020.46
Add 1 % Water charges on “W”
+10.20
TOTAL
1,030.66
Add GST on “X” (multiplying factor 0.2127)
+219.22
TOTAL
1,249.88
Add 15% CPOH on “Y”
+187.48
TOTAL
1,437.36
Add Cess @ 1% on “Z”
+14.37
Cost of 2 m
1,451.73
Cost of 1 metre
725.87
SAY
₹725.85
D-02/SOURCEPRINTED PAGE 497
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
497

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 497. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.