Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : 2nd class teak wood

50 x 20 mm

Item number
9.40.1.2
Analysis basis
Details of cost for beading for 10 window of size
Priced inputs
4
Derived rate
271.75 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.40.1.2 Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : 2nd class teak wood 50 x 20 mm — is derived from 4 priced inputs for beading for and works out to ₹271.75 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 140x110cm i.e. 10x500cm long (50 metre)
  • Teak wood IInd class in planks= 50x0.05x0.02
  • m = 0.05cum+
  • Total = 0.055 cum. Say 55 cudm.
  • Painting with priming coat Area =
  • 50(0.05+0.02+0.02) = 4.5 sqm
  • For plaining, fixing and making design
  • Add for wastage @ 10% = 0.005 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterial10 cudm5.5791.004,350.50
0637Bright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mmMaterial100 Nos3.662.00223.20
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm4.570.35316.58
0111Carpenter 1st classLabourday5.3897.004,754.10
TOTAL
9,644.38
Add 1 % Water charges on “W-A”
93.28
TOTAL
9,737.66
Add GST on “X-A” (multiplying factor 0.2127)
2,003.86
TOTAL
11,741.52
Add 15% CPOH on “Y-A”
1,713.74
TOTAL
13,455.26
Add Cess @ 1% on “Z-A”
131.39
Cost of 50 metre
13,586.65
Cost of 1 metre
271.73
Say
271.75

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 493. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works