Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : 2nd class teak wood

50x12 mm

Item number
9.40.1.1
Analysis basis
Details of cost for beading for 10 window of size
Priced inputs
4
Derived rate
221.10 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.40.1.1 Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : 2nd class teak wood 50x12 mm — is derived from 4 priced inputs for beading for and works out to ₹221.10 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 140x110cm i.e. 10x500cm long (50 metre)
  • Teak wood IInd class in planks = 50x0.05x0.012
  • m = 0.03 cum+
  • Total = 0.033 cum. Say 33 cudm.
  • Painting with priming coat Area =
  • 50(0.05+0.012+0.012) = 3.70 sqm
  • For plaining, fixing and making design
  • Add for wastage @ 10% = 0.003 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
1190Second class teak wood in planksMaterial10 cudm3.3791.002,610.30
0637Bright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mmMaterial100 Nos3.662.00223.20
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm3.770.35260.30
0111Carpenter 1st classLabourday5.3897.004,754.10
TOTAL
7,847.90
Add 1 % Water charges on “W-A”
75.88
TOTAL
7,923.78
Add GST on “X-A” (multiplying factor 0.2127)
1,630.02
TOTAL
9,553.80
Add 15% CPOH on “Y-A”
1,394.03
TOTAL
10,947.83
Add Cess @ 1% on “Z-A”
106.88
Cost of 50 metre
11,054.71
Cost of 1 metre
221.09
Say
221.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 492. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.