CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : Kiln seasoned and chemically treated hollock wood

50x12 mm

Item number
9.40.2.1
Analysis basis
Details of cost for beading for 10 window of size
Priced inputs
5
Derived rate
185.95 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.40.2.1 Providing and fixing wooden moulded beading to door and window frames with iron screws, plugs and priming coat on unexposed surface etc. complete : Kiln seasoned and chemically treated hollock wood 50x12 mm — is derived from 5 priced inputs for beading for and works out to ₹185.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • 140x110cm i.e. 10x500cm long (50 metre)
  • Hollock wood = 50x0.05x0.012 m = 0.03 cum+
  • Total = 0.033 cum. Say 33 cudm.
  • Painting with priming coat Area =
  • 50(0.05+0.012+0.012) = 3.70 sqm
  • For plaining, fixing and making design
  • Add for wastage @ 10% = 0.003 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
2505Hollock wood in planksMaterial10 cudm3.3409.001,349.70
2504Kiln seasoning of timberMaterialcum0.033794.0026.20
0637Bright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mmMaterial100 Nos3.662.00223.20
Rate as per item no 13.85.1 of SH : FinishingRate as per item 13.85.1Sub-analysissqm3.770.35260.30
0111Carpenter 1st classLabourday5.3897.004,754.10
TOTAL
6,613.50
Add 1 % Water charges on “W-A”
63.53
TOTAL
6,677.03
Add GST on “X-A” (multiplying factor 0.2127)
1,364.84
TOTAL
8,041.87
Add 15% CPOH on “Y-A”
1,167.24
TOTAL
9,209.11
Add Cess @ 1% on “Z-A”
89.49
Cost of 50 metre
9,298.60
Cost of 1 metre
185.97
Say
185.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 493. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works