Extra for additional labour for circular works, such as in frames of fan light

Kiln seasoned and chemically treated hollock wood
Item number
9.4.3
Analysis basis
Chowkhat of
Priced inputs
5
Derived rate
₹8,338.10/ CHOWKHAT OF
D-01/RATE ANALYSISITEM 9.4.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.4.3 (Extra for additional labour for circular works, such as in frames of fan light Kiln seasoned and chemically treated hollock wood) is derived from 5 priced inputs for Chowkhat of and works out to ₹8,338.10 per chowkhat of after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 206.75 x 117.5cm. (360 cudm)
  • Extra Materials and labour for wastage @ 10%
  • on quantity of item no 9.1.3
ANALYSIS OF RATES · ITEM 9.4.3DETAILS OF COST FOR CHOWKHAT OF 10 NOS. DOOR
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2466MATHollock wood in scantling10 cudm3.8366.001,390.80
2504MATKiln seasoning of timbercum0.038794.0030.17
9999MATChemical treatmentL.S.92.2720.43
0156LABCarpenter (average)day0.72857.00617.04
0114LABBeldarday0.07736.0051.52
BUILD-UP TO RATE
TOTAL
2,109.96
Add 1 % Water charges on “W”
+21.10
TOTAL
2,131.06
Add GST on “X” (multiplying factor 0.2127)
+453.28
TOTAL
2,584.34
Add 15% CPOH on “Y”
+387.65
TOTAL
2,971.99
Add Cess @ 1% on “Z”
+29.72
Cost of 360 cudm=0.36 cum
3,001.71
Cost per cum.
8,338.08
SAY
₹8,338.10
D-02/SOURCEPRINTED PAGE 440
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
440

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 440. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.