Extra for additional labour for circular works, such as in frames of fan light

Sal wood

Item number
9.4.2
Analysis basis
Details of cost for Chowkhat of 10 Nos. door
Priced inputs
3
Derived rate
11,652.05 / Chowkhat of

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.4.2 Extra for additional labour for circular works, such as in frames of fan light Sal wood — is derived from 3 priced inputs for Chowkhat of and works out to ₹11,652.05 per chowkhat of after water charges, GST, CPOH and cess. The full build-up is below.

  • 206.75 x 117.5cm (360 cudm)
  • Extra Materials and labour for wastage @ 10%
  • on quantity of item no 9.1.2
CodeInputUnitQuantityRate (INR)Amount (INR)
1199Sal wood in scantlingMaterial10 cudm3.8600.002,280.00
0156Carpenter (average)Labourday0.72857.00617.04
0114BeldarLabourday0.07736.0051.52
TOTAL
2,948.56
Add 1 % Water charges on “W”
29.49
TOTAL
2,978.05
Add GST on “X” (multiplying factor 0.2127)
633.43
TOTAL
3,611.48
Add 15% CPOH on “Y”
541.72
TOTAL
4,153.20
Add Cess @ 1% on “Z”
41.53
Cost of 360 cudm=0.36 cum
4,194.73
Cost per cum.
11,652.03
Say
11,652.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 439. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.