CPWD Analysis of Rates · Wood and PVC Work
Extra for additional labour for circular works, such as in frames of fan light
Sal wood
- Item number
- 9.4.2
- Analysis basis
- Details of cost for Chowkhat of 10 Nos. door
- Priced inputs
- 3
- Derived rate
- ₹11,652.05 / Chowkhat of
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.4.2 — Extra for additional labour for circular works, such as in frames of fan light Sal wood — is derived from 3 priced inputs for Chowkhat of and works out to ₹11,652.05 per chowkhat of after water charges, GST, CPOH and cess. The full build-up is below.
- 206.75 x 117.5cm (360 cudm)
- Extra Materials and labour for wastage @ 10%
- on quantity of item no 9.1.2
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1199 | Sal wood in scantlingMaterial | 10 cudm | 3.8 | 600.00 | 2,280.00 |
| 0156 | Carpenter (average)Labour | day | 0.72 | 857.00 | 617.04 |
| 0114 | BeldarLabour | day | 0.07 | 736.00 | 51.52 |
- TOTAL
- 2,948.56
- Add 1 % Water charges on “W”
- 29.49
- TOTAL
- 2,978.05
- Add GST on “X” (multiplying factor 0.2127)
- 633.43
- TOTAL
- 3,611.48
- Add 15% CPOH on “Y”
- 541.72
- TOTAL
- 4,153.20
- Add Cess @ 1% on “Z”
- 41.53
- Cost of 360 cudm=0.36 cum
- 4,194.73
- Cost per cum.
- 11,652.03
- Say
- 11,652.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 439. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.