Extra for additional labour for circular works, such as in frames of fan light
- Item number
- 9.4.1
- Analysis basis
- Chowkhat of
- Priced inputs
- 3
- Derived rate
- ₹14,294.95/ CHOWKHAT OF
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.4.1 (Extra for additional labour for circular works, such as in frames of fan light Second class teak wood) is derived from 3 priced inputs for Chowkhat of and works out to ₹14,294.95 per chowkhat of after water charges, GST, CPOH and cess. The full build-up is below.
- 206.75 x 117.5cm (360 cudm)
- Extra Materials and labour for wastage @ 10%
- on quantity of item no 9.1.1
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1189 | MAT | Second class teak wood in scantling | 10 cudm | 3.8 | 776.00 | 2,948.80 |
| 0156 | LAB | Carpenter (average) | day | 0.72 | 857.00 | 617.04 |
| 0114 | LAB | Beldar | day | 0.07 | 736.00 | 51.52 |
- TOTAL
- 3,617.36
- Add 1 % Water charges on “W”
- +36.17
- TOTAL
- 3,653.53
- Add GST on “X” (multiplying factor 0.2127)
- +777.11
- TOTAL
- 4,430.64
- Add 15% CPOH on “Y”
- +664.60
- TOTAL
- 5,095.24
- Add Cess @ 1% on “Z”
- +50.95
- Cost of 360 cudm=0.36 cum
- 5,146.19
- Cost per cum.
- 14,294.97
- SAY
- ₹14,294.95
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 439
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 439. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.