Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position with necessary stainless steel screws etc
- Item number
- 9.3.2
- Analysis basis
- ceiling for
- Priced inputs
- 6
- Derived rate
- ₹71,337.85/ CEILING FOR
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.3.2 (Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position with necessary stainless steel screws etc Kiln seasoned and chemically treated hollock wood) is derived from 6 priced inputs for ceiling for and works out to ₹71,337.85 per ceiling for after water charges, GST, CPOH and cess. The full build-up is below.
- (158 cudm)
- Hollock wood = 6x3.30x(50/1000)
- x(125/1000)=0.1238 cum. +
- Cross battens 60mm centre to center
- 38x50mm.
- 6x3x(38/1000)x50/1000)=0.0342 cum.
- = 0.1580 cum.+
- = 0.1659 cum. say 166 cudm.
- Add for wastage @ 5% = 0.0079 cum.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2466 | MAT | Hollock wood in scantling | 10 cudm | 16.6 | 366.00 | 6,075.60 |
| 2504 | MAT | Kiln seasoning of timber | cum | 0.166 | 794.00 | 131.80 |
| 9999 | MAT | Chemical treatment | L.S. | 18.2 | 2.27 | 41.31 |
| 0112 | LAB | Carpenter 2nd class | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
| 9999 | MAT | Sundries screws etc. | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 7,922.88
- Add 1 % Water charges on “W”
- +79.23
- TOTAL
- 8,002.11
- Add GST on “X” (multiplying factor 0.2127)
- +1,702.05
- TOTAL
- 9,704.16
- Add 15% CPOH on “Y”
- +1,455.62
- TOTAL
- 11,159.78
- Add Cess @ 1% on “Z”
- +111.60
- Cost of 158 cudm (finished work)
- 11,271.38
- Cost per cum.
- 71,337.85
- SAY
- ₹71,337.85
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 438
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 438. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.