CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing cupboard shutter with 19mm thick one side decorative and other side balancing lamination factory pressed BWP grade marine ply as per IS 710 of approved brand including 2mm thick PVC edge banding tape with hot glue by edge bending machine etc. with auto closing spring loaded hinges (hydraulic type) etc. complete as per direction of Engineerin-charge.(Payment of providing and fixing auto closing hinges shall be paid separately)

Item number
9.168
Analysis basis
Details of cost for 2.2 sqm.
Priced inputs
5
Derived rate
2,829.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.168 Providing and fixing cupboard shutter with 19mm thick one side decorative and other side balancing lamination factory pressed BWP grade marine ply as per IS 710 of approved brand including 2mm thick PVC edge banding tape with hot glue by edge bending machine etc. with auto closing spring loaded hinges (hydraulic type) etc. complete as per direction of Engineerin-charge.(Payment of providing and fixing auto closing hinges shall be paid separately) — is derived from 5 priced inputs for 2.2 sqm and works out to ₹2,829.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • For fixing shutter and PVC edge bending tape
CodeInputUnitQuantityRate (INR)Amount (INR)
249719mm thick prelaminated ply 2.20sqm.+ Add wastage @ 5% = 0.11 sqm. Total = 2.31 sqm19 mm thick prelaminated plyMaterialsqm2.311,530.003,534.30
9977Carriage of shutterMaterialL.S.29.642.2767.28
2489PVC edge bending tape 2 X (2.00+1.10)= 6.20 metrePVC edge bending tape 2.00 mm thickMaterialmetre6.222.00136.40
0156Carpenter (average)Labourday0.4857.00342.80
0114BeldarLabourday0.4736.00294.40
TOTAL
4,375.18
Add 1 % Water charges on “W”
43.75
TOTAL
4,418.93
Add GST on “X” (multiplying factor 0.2127)
939.91
TOTAL
5,358.84
Add 15% CPOH on “Y”
803.83
TOTAL
6,162.67
Add Cess @ 1% on “Z”
61.63
Cost for 2.2 sqm.
6,224.30
Cost of 1 sqm.
2,829.23
Say
2,829.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 706. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.