CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing 19mm thick both side balancing lamination factory pressed BWP grade marine ply as per IS 710 of approved brand boxes,shelves,racks,almirah,cupboard and drawer etc. including necessary nails,screws etc. complete as per direction of Engineer-in-charge

Item number
9.169
Analysis basis
Details of cost for 4 nos.
Priced inputs
5
Derived rate
2,593.15 / nos

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.169 Providing and fixing 19mm thick both side balancing lamination factory pressed BWP grade marine ply as per IS 710 of approved brand boxes,shelves,racks,almirah,cupboard and drawer etc. including necessary nails,screws etc. complete as per direction of Engineer-in-charge — is derived from 5 priced inputs for 4 nos and works out to ₹2,593.15 each after water charges, GST, CPOH and cess. The full build-up is below.

  • 75x20cm shelves = 0.60 sqm.
  • 18mm thick particle board
  • 4x75x20cm = 0.60sqm.
  • Total = 0.63 sqm
  • Add wastage @ 5% = 0.03sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
249819mm thick both side balancing lamination factory pressed BWP grade marine ply as per IS 71019 mm thick both side balancing lamination factory pressed BWP grade marine ply as per IS 710Materialsqm0.631,492.00939.96
9977Carriage of boardMaterialL.S.0.912.272.07
0112Carpenter 2nd classLabourday0.11816.0089.76
0114BeldarLabourday0.06736.0044.16
9999Sundries, Painting edges & ScrewsMaterialL.S.7.82.2717.71
TOTAL
1,093.66
Add 1 % Water charges on “W”
10.94
TOTAL
1,104.60
Add GST on “X” (multiplying factor 0.2127)
234.95
TOTAL
1,339.55
Add 15% CPOH on “Y”
200.93
TOTAL
1,540.48
Add Cess @ 1% on “Z”
15.40
Cost of 0.60 sqm.
1,555.88
Cost of 1sqm.
2,593.13
Say
2,593.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 707. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.