CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing 6mm thick both sides Pre-laminated cement bonded wood particle board as per IS : 15786:2008 of approved brand and shade with suitable full threaded steel screws etc. on the backing of racks, drawer, cupboard, kitchen cabinet under kitchen counter etc. all complete as per direction of Engineer-in-charge
- Item number
- 9.167
- Analysis basis
- Details of cost for 350x200cm = 7sqm.
- Priced inputs
- 5
- Derived rate
- ₹1,010.60 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.167 — Providing and fixing 6mm thick both sides Pre-laminated cement bonded wood particle board as per IS : 15786:2008 of approved brand and shade with suitable full threaded steel screws etc. on the backing of racks, drawer, cupboard, kitchen cabinet under kitchen counter etc. all complete as per direction of Engineer-in-charge — is derived from 5 priced inputs and works out to ₹1,010.60 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 6mm thick board = 7.00sqm.+ Add wastage @
- 5% = 0.35 sqm. Total = 7.35 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2496 | 6mm thick both sides Pre-laminated cement bonded wood particle board as per IS : 15786:20086 mm thick both sides Pre-laminated cement bonded wood particle board as per IS : 15786:2008Material | sqm | 7.35 | 464.00 | 3,410.40 |
| 9977 | Carriage of particle boardMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Sundries and screwsMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 0112 | Carpenter 2nd classLabour | day | 0.9 | 816.00 | 734.40 |
| 0114 | BeldarLabour | day | 1 | 736.00 | 736.00 |
- TOTAL
- 4,972.58
- Add 1 % Water charges on “W”
- 49.73
- TOTAL
- 5,022.31
- Add GST on “X” (multiplying factor 0.2127)
- 1,068.25
- TOTAL
- 6,090.56
- Add 15% CPOH on “Y”
- 913.58
- TOTAL
- 7,004.14
- Add Cess @ 1% on “Z”
- 70.04
- Cost of 7 sqm.
- 7,074.18
- Cost of 1 sqm.
- 1,010.60
- Say
- 1,010.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 706. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.