Skip to main content
R/DAR 2023

Providing and fixing bright /matt finished Stainless Steel handles of approved quality & make with necessary screws etc all complete

75 mm
Item number
9.165.3
Analysis basis
ten nos
Priced inputs
4
Derived rate
₹58.75/ TEN NOS
D-01/RATE ANALYSISITEM 9.165.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.165.3 (Providing and fixing bright /matt finished Stainless Steel handles of approved quality & make with necessary screws etc all complete 75 mm) is derived from 4 priced inputs for ten nos and works out to ₹58.75 per ten nos after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.165.3DETAILS OF COST FOR TEN NOS (75 MM)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0552MATStainless steel fancy handles (75mm) for kitchen cabinet75 mm SS fancy handles for kitchen cabinet10 Nos1285.00285.00
8214MATSS screws 20mmStainless steel screws 20 mmNos.0.4175.0070.00
9999MATCarriage of materialLS1.822.274.13
0111LABCarpenter 1st classday0.06897.0053.82
BUILD-UP TO RATE
TOTAL
412.95
Add 1 % Water charges on “W”
+4.13
TOTAL
417.08
Add GST on “X” (multiplying factor 0.2127)
+88.71
TOTAL
505.79
Add 15% CPOH on “Y”
+75.87
TOTAL
581.66
Add Cess @ 1% on “Z”
+5.82
Cost for 10nos
587.48
Cost for1 no
58.75
SAY
₹58.75
D-02/SOURCEPRINTED PAGE 705
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
705

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 705. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.