Skip to main content
R/DAR 2023

Providing and fixing bright /matt finished Stainless Steel handles of approved quality & make with necessary screws etc all complete

125 mm
Item number
9.165.1
Analysis basis
ten nos
Priced inputs
4
Derived rate
₹119.20/ TEN NOS
D-01/RATE ANALYSISITEM 9.165.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.165.1 (Providing and fixing bright /matt finished Stainless Steel handles of approved quality & make with necessary screws etc all complete 125 mm) is derived from 4 priced inputs for ten nos and works out to ₹119.20 per ten nos after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.165.1DETAILS OF COST FOR TEN NOS (125 MM)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0554MATStainless steel fancy handles (125mm) for kitchen cabinet125 mm SS fancy handles for kitchen cabinet10 Nos1710.00710.00
8214MATSS screws 20mmStainless steel screws 20 mmNos.0.4175.0070.00
9999MATCarriage of materialLS1.822.274.13
0111LABCarpenter 1st classday0.06897.0053.82
BUILD-UP TO RATE
TOTAL
837.95
Add 1 % Water charges on “W”
+8.38
TOTAL
846.33
Add GST on “X” (multiplying factor 0.2127)
+180.01
TOTAL
1,026.34
Add 15% CPOH on “Y”
+153.95
TOTAL
1,180.29
Add Cess @ 1% on “Z”
+11.80
Cost for 10nos
1,192.09
Cost for1 no
119.21
SAY
₹119.20
D-02/SOURCEPRINTED PAGE 704
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
704

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 704. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.