Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing glazing in fire resistant door shutters, fixed panels & partitions etc., with G.I. beading made out of 1.6 mm thick G.I. sheet (zinc coating not less than 120 gm/sqm) of size 20 x 33 mm screwed with M4 x 38 mm SS screws at distance 75 mm from the edges and 150 mm c/c , including applying a coat of approved fire resistant primer/powder coating of not less than 30 micron on G.I. beading, & special ceramic tape of 5 x 20 mm size etc complete in all respect as per NBC 2016, IS 16231 (Part 3):2016 and as per direction of Engineer-inCharge with glass of required thickness having 120 minutes of fire resistance both integrity & radiation control (EW120) and minimum 20 minutes of insulation (EI20). The manufacturer have to give test report/certification of fire glass and the glass should have the stamp showing the value of E, EW & EI. The glass shall be tested in approved NABL accredited lab or by any other accreditation body which operates in accordance with ISO/IEC 17011 and accredited labs as per ISO/IEC 17025 for testing and calibration scopes shall be eligible. The maximum glazing size shall not be more than 1100x2200 mm (w x h) or 2.42 sqm

Item number
9.164
Analysis basis
Details of cost for glazing portion 2.46 sqm
Priced inputs
5
Derived rate
43,677.65 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.164 Providing and fixing glazing in fire resistant door shutters, fixed panels & partitions etc., with G.I. beading made out of 1.6 mm thick G.I. sheet (zinc coating not less than 120 gm/sqm) of size 20 x 33 mm screwed with M4 x 38 mm SS screws at distance 75 mm from the edges and 150 mm c/c , including applying a coat of approved fire resistant primer/powder coating of not less than 30 micron on G.I. beading, & special ceramic tape of 5 x 20 mm size etc complete in all respect as per NBC 2016, IS 16231 (Part 3):2016 and as per direction of Engineer-inCharge with glass of required thickness having 120 minutes of fire resistance both integrity & radiation control (EW120) and minimum 20 minutes of insulation (EI20). The manufacturer have to give test report/certification of fire glass and the glass should have the stamp showing the value of E, EW & EI. The glass shall be tested in approved NABL accredited lab or by any other accreditation body which operates in accordance with ISO/IEC 17011 and accredited labs as per ISO/IEC 17025 for testing and calibration scopes shall be eligible. The maximum glazing size shall not be more than 1100x2200 mm (w x h) or 2.42 sqm — is derived from 5 priced inputs for glazing portion and works out to ₹43,677.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • (Door size 1710 mm x 2050 mm)
  • Glazing area- 2x0.679x1.808= 2.46 sqm
  • MATERIAL:
  • LABOUR:
CodeInputUnitQuantityRate (INR)Amount (INR)
2640Glass panes of required thickness having 120 minutes of fire resistance both integrity and radiation control (EW120) and minimum 20 minutes of insulation (EI 20)Glass panes of required thickness having 120 minutes of fire resistance both integrity and radiation control (EI 120) and minimum 20 minutes of insulation (EI 20)Materialsqm2.4626,200.0064,452.00
2641G.I. U beading of 1.6 mm thick G.I. Sheet with M4x38mm SS screwsG.I U beading of 1.6 mm thick G.I sheet with ceramic tape.Materialmetre9.91256.002,536.96
2642Ceramic tape 5x20 mm sizeCeramic tape 5 x20 mm sizeMaterialmetre19.82409.008,106.38
9999For fixing in position all completeMaterialL.S.1802.27408.60
9999Sundries and carriage & Calcium Silicate BlocksMaterialL.S.102.2722.70
TOTAL
75,526.64
Add 1 % Water charges on “W”
755.27
TOTAL
76,281.91
Add GST on “X” (multiplying factor 0.2127)
16,225.16
TOTAL
92,507.07
Add 15% CPOH on “Y”
13,876.06
TOTAL
1,06,383.13
Add Cess @ 1% on “Z”
1,063.83
Cost of 2.46 sqm
1,07,446.96
Cost of 1 sqm
43,677.63
Say
43,677.65

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 703. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.