CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing non load bearing fixed frame for fire resistant glazed partition for 120 minutes fire rating, made out to a profile of dimension 60mm x 70 mm of 1.6 mm thick galvanised steel sheet as per test evidence suitable for fixing fire rated glass for 120 minutes of both integrity & radiation control (EW120) & minimum 20 minutes of insulation (EI20).The profile has to be fixed to the supporting construction by means of anchor fasteners of size M10 x 80, every 150 mm from the edges and every 500 mm (approx) c/c. Linear measurement of frame shall be measured for payment. The frame shall be filled with mineral wool insulation of density minimum 96kg/ cum and finished with a approved fire resistant primer or powder coating of not less than 30 micron in desired shade as per NBC 2016, IS 16231 (Part 3):2016 and directions of Engineer - inCharge
- Item number
- 9.163
- Analysis basis
- Details of cost for 5.81 metre (2.05+1.71+2.05)
- Priced inputs
- 3
- Derived rate
- ₹2,202.90 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.163 — Providing and fixing non load bearing fixed frame for fire resistant glazed partition for 120 minutes fire rating, made out to a profile of dimension 60mm x 70 mm of 1.6 mm thick galvanised steel sheet as per test evidence suitable for fixing fire rated glass for 120 minutes of both integrity & radiation control (EW120) & minimum 20 minutes of insulation (EI20).The profile has to be fixed to the supporting construction by means of anchor fasteners of size M10 x 80, every 150 mm from the edges and every 500 mm (approx) c/c. Linear measurement of frame shall be measured for payment. The frame shall be filled with mineral wool insulation of density minimum 96kg/ cum and finished with a approved fire resistant primer or powder coating of not less than 30 micron in desired shade as per NBC 2016, IS 16231 (Part 3):2016 and directions of Engineer - inCharge — is derived from 3 priced inputs for 5.81 metre and works out to ₹2,202.90 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- (Door size- 1710 x 2050 mm)
- MATERIAL:
- LABOUR:
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8017 | Fire Rated door Frame made with 1.6 mm thick G.I. Sheet (120 minutes)Fire rated door frame made with 1.6 mm thick G.I sheet (120 minutes fire rating)Material | metre | 5.81 | 1,400.00 | 8,134.00 |
| 9999 | For fixing in position all completeMaterial | L.S. | 130 | 2.27 | 295.10 |
| 9999 | Sundries and carriage ( Fasteners, sims, Hole Plugs etc)Material | L.S. | 250 | 2.27 | 567.50 |
- TOTAL
- 8,996.60
- Add 1 % Water charges on “W”
- 89.97
- TOTAL
- 9,086.57
- Add GST on “X” (multiplying factor 0.2127)
- 1,932.71
- TOTAL
- 11,019.28
- Add 15% CPOH on “Y”
- 1,652.89
- TOTAL
- 12,672.17
- Add Cess @ 1% on “Z”
- 126.72
- Cost of 5.81 mtere
- 12,798.89
- Cost of 1 metre
- 2,202.91
- Say
- 2,202.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 702. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works