CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing skirting with Pre-laminated medium density fibre board exterior grade (Grade-I) conforming to IS: 14587:1998 marked, with (one side decorative and other side balancing lamination and edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. all complete
18 mm thick
- Item number
- 9.160.1
- Analysis basis
- Detail of cost for skirting 200 mm wide & 30 m
- Priced inputs
- 8
- Derived rate
- ₹2,076.65 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.160.1 — Providing and fixing skirting with Pre-laminated medium density fibre board exterior grade (Grade-I) conforming to IS: 14587:1998 marked, with (one side decorative and other side balancing lamination and edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. all complete 18 mm thick — is derived from 8 priced inputs for skirting 200 and works out to ₹2,076.65 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- long
- Area 0.20 mx30 m = 6.0 sqm
- Total = 6.60 sqm
- Add wastage @ 10 % = 0.60 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2488 | Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 18 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 18 mm thick conforming to IS:14587Material | sqm | 6.6 | 599.00 | 3,953.40 |
| 9999 | Sundries (Carriage of MDF board)Material | L.S. | 8.11 | 2.27 | 18.41 |
| 2489 | PVC edge bending tape 2.00 mm thickMaterial | metre | 30 | 22.00 | 660.00 |
| 7048 | Rawl plug 50 mm (designation 10 nos)Rawl plug 50 mm (designation 10)Material | each | 102 | 24.00 | 2,448.00 |
| 9999 | Sundries (Labour for drilling hole)Material | L.S. | 130 | 2.27 | 295.10 |
| 0112 | Carpenter 2nd classLabour | day | 0.77 | 816.00 | 628.32 |
| 0114 | BeldarLabour | day | 0.86 | 736.00 | 632.96 |
| 9999 | Sundries ( screws and sand paper)Material | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 8,758.36
- Add 1 % Water charges on “W”
- 87.58
- TOTAL
- 8,845.94
- Add GST on “X” (multiplying factor 0.2127)
- 1,881.53
- TOTAL
- 10,727.47
- Add 15% CPOH on “Y”
- 1,609.12
- TOTAL
- 12,336.59
- Add Cess @ 1% on “Z”
- 123.37
- Cost of 6.00 sqm.
- 12,459.96
- Cost of 1 sqm.
- 2,076.66
- Say
- 2,076.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 699. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works