Providing and fixing skirting with Pre-laminated medium density fibre board exterior grade (Grade-I) conforming to IS: 14587:1998 marked, with (one side decorative and other side balancing lamination and edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. all complete

25 mm thick

Item number
9.160.2
Analysis basis
Detail of cost for skirting 200 mm wide & 30 m
Priced inputs
8
Derived rate
2,552.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.160.2 Providing and fixing skirting with Pre-laminated medium density fibre board exterior grade (Grade-I) conforming to IS: 14587:1998 marked, with (one side decorative and other side balancing lamination and edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand with necessary fixing arrangements and screws, including drilling necessary holes for rawl plugs etc. all complete 25 mm thick — is derived from 8 priced inputs for skirting 200 and works out to ₹2,552.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • long
  • Area 0.20 mx30 m = 6.0 sqm
  • Total = 6.60 sqm
  • Add wastage @ 10 % = 0.60 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2486Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 25 mm thick conforming to IS: 14587Materialsqm6.6903.005,959.80
9999Sundries (Carriage of MDF board)MaterialL.S.8.112.2718.41
2489PVC edge bending tape 2.00 mm thickMaterialmetre3022.00660.00
7048Rawl plug 50 mm (designation 10 nos)Rawl plug 50 mm (designation 10)Materialeach10224.002,448.00
9999Sundries (Labour for drilling hole)MaterialL.S.1302.27295.10
0112Carpenter 2nd classLabourday0.77816.00628.32
0114BeldarLabourday0.86736.00632.96
9999Sundries ( screws and sand paper)MaterialL.S.53.822.27122.17
TOTAL
10,764.76
Add 1 % Water charges on “W”
107.65
TOTAL
10,872.41
Add GST on “X” (multiplying factor 0.2127)
2,312.56
TOTAL
13,184.97
Add 15% CPOH on “Y”
1,977.75
TOTAL
15,162.72
Add Cess @ 1% on “Z”
151.63
Cost of 6.00 sqm.
15,314.35
Cost of 1 sqm.
2,552.39
Say
2,552.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 700. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.