CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing 25mm thick pre-laminated medium density fibre board exterior grade ( Grade-I) IS:14587:1998 marked with one side decorative and other side balancing lamination for cupboard shutters edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand including ISI marked nickel plated bright finishing M.S. piano hinges conforming to IS:3818 marked with necessary screw etc all complete

Item number
9.159
Analysis basis
Details of cost for 2.20 sqm (2.20 m x 1.00 m)
Priced inputs
7
Derived rate
2,135.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.159 Providing and fixing 25mm thick pre-laminated medium density fibre board exterior grade ( Grade-I) IS:14587:1998 marked with one side decorative and other side balancing lamination for cupboard shutters edges to be sealed with PVC edge bending tape 2.00 mm thick of approved brand including ISI marked nickel plated bright finishing M.S. piano hinges conforming to IS:3818 marked with necessary screw etc all complete — is derived from 7 priced inputs for 2.20 sqm and works out to ₹2,135.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • PVC edge bending tape 2.00 mm thick
  • 2x(2.20+1.00)=6.40 metre
  • Fitting for a door of 2.20 m x1.00 m
  • Total = 2( 2.20) = 4.40 metre
  • For fixing shutter and fittings
CodeInputUnitQuantityRate (INR)Amount (INR)
2486Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 25 mm thick conforming to IS: 14587Materialsqm2.2903.001,986.60
9999Sundries (Carriage of MDF board)MaterialL.S.26.942.2761.15
2489PVC edge bending tape 2.00 mm thickMaterialmetre6.422.00140.80
0608Nickel plated bright finished mild steel piano hinges 1 mm thick 25 mm wideMaterialmetre4.442.00184.80
0639Bright finished or black enameled mild steel screws 25 mmMaterial100 Nos1.2542.0052.50
0156Carpenter (average)Labourday0.55857.00471.35
0114BeldarLabourday0.55736.00404.80
TOTAL
3,302.00
Add 1 % Water charges on “W”
33.02
TOTAL
3,335.02
Add GST on “X” (multiplying factor 0.2127)
709.36
TOTAL
4,044.38
Add 15% CPOH on “Y”
606.66
TOTAL
4,651.04
Add Cess @ 1% on “Z”
46.51
Cost of 2.20 sqm.
4,697.55
Cost of 1 sqm.
2,135.25
Say
2,135.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 699. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works