CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing in wall lining medium density fibre board IS: 14587:1998 marked, Prelaminated one side decorative lamination and other side balancing lamination, with necessary fixing arrangement and screws etc. complete

25 mm thick

Item number
9.158.3
Analysis basis
Details of cost for 10.00 sqm
Priced inputs
6
Derived rate
1,912.25 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.158.3 Providing and fixing in wall lining medium density fibre board IS: 14587:1998 marked, Prelaminated one side decorative lamination and other side balancing lamination, with necessary fixing arrangement and screws etc. complete 25 mm thick — is derived from 6 priced inputs for 10.00 sqm and works out to ₹1,912.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 25 mm thick MDF Board Grade-I ,one side laminated = 10.00 sqm
  • Total= 11.00 sqm
  • Add wastage @10 % = 1.00 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2486Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 25 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 25 mm thick conforming to IS: 14587Materialsqm11903.009,933.00
9999Sundries (Carriage of MDF board)MaterialL.S.13.522.2730.69
9999Sundries and screwsMaterialL.S.26.912.2761.09
0112Carpenter 2nd classLabourday1.28816.001,044.48
0114BeldarLabourday1.43736.001,052.48
7048Rawl plug 50 mm (designation 10 nos)Rawl plug 50 mm (designation 10)Materialeach5524.001,320.00
TOTAL
13,441.74
Add 1 % Water charges on “W”
134.42
TOTAL
13,576.16
Add GST on “X” (multiplying factor 0.2127)
2,887.65
TOTAL
16,463.81
Add 15% CPOH on “Y”
2,469.57
TOTAL
18,933.38
Add Cess @ 1% on “Z”
189.33
Cost of 10.00 sqm.
19,122.71
Cost of 1 sqm.
1,912.27
Say
1,912.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 698. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.