Providing and fixing in wall lining medium density fibre board IS: 14587:1998 marked, Prelaminated one side decorative lamination and other side balancing lamination, with necessary fixing arrangement and screws etc. complete

18 mm thick
Item number
9.158.2
Analysis basis
10.00 sqm
Priced inputs
6
Derived rate
₹1,436.55/ SQM
D-01/RATE ANALYSISITEM 9.158.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.158.2 (Providing and fixing in wall lining medium density fibre board IS: 14587:1998 marked, Prelaminated one side decorative lamination and other side balancing lamination, with necessary fixing arrangement and screws etc. complete 18 mm thick) is derived from 6 priced inputs for 10.00 sqm and works out to ₹1,436.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 18 mm thick MDF Board Grade-I ,one side laminated = 10.00 sqm
  • Total= 11.00 sqm
  • Add wastage @10 % = 1.00 sqm
ANALYSIS OF RATES · ITEM 9.158.2DETAILS OF COST FOR 10.00 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2488MATPre-laminated with decorative lamination one side and other side balancing lamination exterior Grade - I MDF Board 18 mm thick conforming to IS:14587Pre-laminated with decorative lamination one side and other side balancing lamination exterior Grade-I MDF Board 18 mm thick conforming to IS:14587sqm11599.006,589.00
9999MATSundries (Carriage of MDF board)L.S.13.522.2730.69
9999MATSundries and screwsL.S.26.912.2761.09
0112LABCarpenter 2nd classday1.28816.001,044.48
0114LABBeldarday1.43736.001,052.48
7048MATRawl plug 50 mm (designation 10 nos)Rawl plug 50 mm (designation 10)each5524.001,320.00
BUILD-UP TO RATE
TOTAL
10,097.74
Add 1 % Water charges on “W”
+100.98
TOTAL
10,198.72
Add GST on “X” (multiplying factor 0.2127)
+2,169.27
TOTAL
12,367.99
Add 15% CPOH on “Y”
+1,855.20
TOTAL
14,223.19
Add Cess @ 1% on “Z”
+142.23
Cost of 10.00 sqm.
14,365.42
Cost of 1 sqm.
1,436.54
SAY
₹1,436.55
D-02/SOURCEPRINTED PAGE 697
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
697

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 697. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.