CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing 25 mm thick shutters for cup board etc. : Glazed shutters
Second class teak wood including ISI marked anodized aluminium butt hinges with necessary screws
- Item number
- 9.16.2.1
- Analysis basis
- Details of cost for shutter of cup-board
- Priced inputs
- 8
- Derived rate
- ₹4,193.25 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.16.2.1 — Providing and fixing 25 mm thick shutters for cup board etc. : Glazed shutters : Second class teak wood including ISI marked anodized aluminium butt hinges with necessary screws — is derived from 8 priced inputs for shutter of and works out to ₹4,193.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 2000x108cm = 2.16 sqm.
- (i) Teak wood second class
- Styles : 4x200x9.5x2.5 cm = 0.019 cum
- Rails
- Top & intermediate rails
- 2x110.5x9.5x2.5 cm = 0.006 cum
- Lock and bottom rails
- 2x110.5x19.7x2.5 cm = 0.011 cum
- Beadings2x186.1x1.9x1.2cm = 0.001cum+
- 4x171.70x1.9x1.2cm = 0.002cum.
- Total = 0.039 cum.
- Grand Total = 0.043 cum. 43 cudm
- Add for wastage @ 10% = 0.004 cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1190 | Second class teak wood in planksMaterial | 10 cudm | 4.3 | 791.00 | 3,401.30 |
| 2406 | Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)Material | sqm | 1.27 | 321.00 | 407.67 |
| 0694 | Anodised Aluminium butt hinges 75x45x3.2 mmMaterial | 10 Nos | 0.6 | 205.00 | 123.00 |
| 0639 | Bright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mmMaterial | 100 Nos | 0.48 | 42.00 | 20.16 |
| 0156 | Carpenter (average)Labour | day | 1.83 | 857.00 | 1,568.31 |
| 0119 | GlazierLabour | day | 0.23 | 816.00 | 187.68 |
| 0114 | BeldarLabour | day | 0.77 | 736.00 | 566.72 |
| 9999 | SundriesMaterial | L.S. | 40.43 | 2.27 | 91.78 |
- TOTAL
- 6,366.62
- Add 1 % Water charges on “W”
- 63.67
- TOTAL
- 6,430.29
- Add GST on “X” (multiplying factor 0.2127)
- 1,367.72
- TOTAL
- 7,798.01
- Add 15% CPOH on “Y”
- 1,169.70
- TOTAL
- 8,967.71
- Add Cess @ 1% on “Z”
- 89.68
- Cost of 2.16 sqm.
- 9,057.39
- Cost of 1 sqm.
- 4,193.24
- Say
- 4,193.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 468. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.