CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing 25 mm thick shutters for cup board etc. : Panelled or panelled & glazed shutters
Second class teak wood including ISI marked nickel plated bright finished M.S. piano hinges with necessary screws
- Item number
- 9.16.1.2
- Analysis basis
- Details of cost for shutters of a cup-board (half
- Priced inputs
- 8
- Derived rate
- ₹4,542.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.16.1.2 — Providing and fixing 25 mm thick shutters for cup board etc. : Panelled or panelled & glazed shutters : Second class teak wood including ISI marked nickel plated bright finished M.S. piano hinges with necessary screws — is derived from 8 priced inputs for shutters of and works out to ₹4,542.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- glazed and half panelled) 200x108cm = 2.16
- sqm.
- Styles4x200x8.0x2.5cm = 0.016 cum+
- RailsTop rail1x110.5x8.0x2.5cm = 0.0022cum+
- Lock and bottom rail2x110.5x8.0x2.5cm = 0.0044 cum.
- Panels2x48x41x1.6cm = 0.006cum+
- Sash bars2x114x3.8x2.5cm = 0.003cum+
- 6x48x3.8x2.5cm = 0.003 cum+
- Beading16x92x1.4x1.2cm = 0.002cum
- Total = 0.0366
- Grand Total = 0.0403 cum or 40 cudm
- Fittings-
- Add for wastage @ 10% = 0.0037 cum.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1190 | Second class teak wood in planksMaterial | 10 cudm | 4 | 791.00 | 3,164.00 |
| 2406 | Float glass sheet of nominal thickness 4 mm (weight not less than 10kg/sqm)Float glass panes of nominal thickness 4 mm (weight not less than 10 kg/sqm)Material | sqm | 0.99 | 321.00 | 317.79 |
| 0608 | Nickel plated mild steel piono hinges 1 mm thick 25 mm wideNickel plated bright finished mild steel piano hinges 1 mm thick 25 mm wideMaterial | metre | 4 | 42.00 | 168.00 |
| 0586 | Chromium plated Brass screws 40 mmMaterial | 100 Nos | 1.14 | 254.00 | 289.56 |
| 0111 | Carpenter 1st classLabour | day | 2.4 | 897.00 | 2,152.80 |
| 0119 | GlazierLabour | day | 0.18 | 816.00 | 146.88 |
| 0114 | BeldarLabour | day | 0.77 | 736.00 | 566.72 |
| 9999 | SundriesMaterial | L.S. | 40.43 | 2.27 | 91.78 |
- TOTAL
- 6,897.53
- Add 1 % Water charges on “W”
- 68.98
- TOTAL
- 6,966.51
- Add GST on “X” (multiplying factor 0.2127)
- 1,481.78
- TOTAL
- 8,448.29
- Add 15% CPOH on “Y”
- 1,267.24
- TOTAL
- 9,715.53
- Add Cess @ 1% on “Z”
- 97.16
- Cost of 2.16 sqm.
- 9,812.69
- Cost of 1 sqm.
- 4,542.91
- Say
- 4,542.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 467. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.