Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing Pre -laminated medium density fibre board exterior grade (Grade-I) IS:14587:1998 marked, to frame, backing or studding with screws etc. complete ( Frames, backing or studding to be paid separately)

Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587

Item number
9.156.1
Analysis basis
Detail of cost for 350x200 cm = 7sqm
Priced inputs
5
Derived rate
1,031.50 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.156.1 Providing and fixing Pre -laminated medium density fibre board exterior grade (Grade-I) IS:14587:1998 marked, to frame, backing or studding with screws etc. complete ( Frames, backing or studding to be paid separately) Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587 — is derived from 5 priced inputs for 350x200 cm and works out to ₹1,031.50 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 12 mm thick both side laminated board = 7.00
  • sqm
  • Total= 7.35 sqm
  • Add for wastage @5% = 0.35 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
2484Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587Pre-laminated with decorative lamination on both side exterior Grade-I MDF Board 12 mm thick conforming to IS:14587Materialsqm7.35478.003,513.30
9999Sundries (Carriage of MDF board)MaterialL.S.13.522.2730.69
9999Sundries and screwsMaterialL.S.26.912.2761.09
0112Carpenter 2nd classLabourday0.9816.00734.40
0114BeldarLabourday1736.00736.00
TOTAL
5,075.48
Add 1 % Water charges on “W”
50.75
TOTAL
5,126.23
Add GST on “X” (multiplying factor 0.2127)
1,090.35
TOTAL
6,216.58
Add 15% CPOH on “Y”
932.49
TOTAL
7,149.07
Add Cess @ 1% on “Z”
71.49
Cost of 7.00 sqm.
7,220.56
Cost of 1 sqm.
1,031.51
Say
1,031.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 694. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works