Providing and fixing Pre -laminated medium density fibre board exterior grade (Grade-I) IS:14587:1998 marked, to frame, backing or studding with screws etc. complete ( Frames, backing or studding to be paid separately)
- Item number
- 9.156.2
- Analysis basis
- 350x200 cm
- Priced inputs
- 5
- Derived rate
- ₹1,248.00/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.156.2 (Providing and fixing Pre -laminated medium density fibre board exterior grade (Grade-I) IS:14587:1998 marked, to frame, backing or studding with screws etc. complete ( Frames, backing or studding to be paid separately) Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 18 mm thick conforming to IS:14587) is derived from 5 priced inputs for 350x200 cm and works out to ₹1,248.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 18 mm thick both side laminated board = 7.00
- sqm
- Total= 7.35 sqm
- Add for wastage @5% = 0.35 sqm
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 2485 | MAT | Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 18 mm thick conforming to IS:14587Pre-laminated with decorative lamination on both side exterior Grade-I MDF Board 18 mm thick conforming to IS:14587 | sqm | 7.35 | 621.00 | 4,564.35 |
| 9999 | MAT | Sundries (Carriage of MDF board) | L.S. | 19.76 | 2.27 | 44.86 |
| 9999 | MAT | Sundries and screws | L.S. | 26.91 | 2.27 | 61.09 |
| 0112 | LAB | Carpenter 2nd class | day | 0.9 | 816.00 | 734.40 |
| 0114 | LAB | Beldar | day | 1 | 736.00 | 736.00 |
- TOTAL
- 6,140.70
- Add 1 % Water charges on “W”
- +61.41
- TOTAL
- 6,202.11
- Add GST on “X” (multiplying factor 0.2127)
- +1,319.19
- TOTAL
- 7,521.30
- Add 15% CPOH on “Y”
- +1,128.20
- TOTAL
- 8,649.50
- Add Cess @ 1% on “Z”
- +86.50
- Cost of 7.00 sqm.
- 8,736.00
- Cost of 1 sqm.
- 1,248.00
- SAY
- ₹1,248.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 695
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 695. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.