CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing panelling or paneling and glazing in panelled or panelled and glazed shutters for doors, windows and clerestory windows ( area of opening for panel inserts excluding portion inside grooves or rebated to be measured). Panelling for panelled and glazed shutters 25mm to 40mm thick: Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587
- Item number
- 9.155
- Analysis basis
- Detail of cost for a door with 2/3rd paneling.
- Priced inputs
- 4
- Derived rate
- ₹1,956.90 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.155 — Providing and fixing panelling or paneling and glazing in panelled or panelled and glazed shutters for doors, windows and clerestory windows ( area of opening for panel inserts excluding portion inside grooves or rebated to be measured). Panelling for panelled and glazed shutters 25mm to 40mm thick: Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587 — is derived from 4 priced inputs for a door and works out to ₹1,956.90 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 200 x 108 cm = 2.16 sqm
- Pannel area 4x45.1x36.55cm = 0.66 sqm
- Both side laminated 12mm thick
- MDF Board 4x47.2x38.65 cm = 0.73 sqm
- Adding 10% wastage = 0.07 sqm
- Total= 0.80 sqm
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 2484 | Pre-laminated with decorative lamination on both side exterior Grade - I MDF Board 12 mm thick conforming to IS:14587Pre-laminated with decorative lamination on both side exterior Grade-I MDF Board 12 mm thick conforming to IS:14587Material | sqm | 0.8 | 478.00 | 382.40 |
| 9999 | Sundries (Carriage of MDF board)Material | L.S. | 1.82 | 2.27 | 4.13 |
| 0111 | Carpenter 1 st classCarpenter 1st classLabour | day | 0.57 | 897.00 | 511.29 |
| 9999 | SundriesMaterial | L.S. | 4.42 | 2.27 | 10.03 |
- TOTAL
- 907.85
- Add 1 % Water charges on “W”
- 9.08
- TOTAL
- 916.93
- Add GST on “X” (multiplying factor 0.2127)
- 195.03
- TOTAL
- 1,111.96
- Add 15% CPOH on “Y”
- 166.79
- TOTAL
- 1,278.75
- Add Cess @ 1% on “Z”
- 12.79
- Cost of 0.66 sqm.
- 1,291.54
- Cost of 1 sqm.
- 1,956.88
- Say
- 1,956.90
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 693. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate