CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing frame work for partitions/ wall lining etc. made of 50x50x1.6 mm hollow MS tube, placed along the walls, ceiling and floor in a grid pattern with spacing @ 60 cm centre to centre both ways (vertically & horizontally) or at required spacing near opening, with necessary welding at junctions and fixing the frame to wall/ ceiling/ floors with steel dash fasteners of 8 mm dia, 75 mm long bolt, including making provision for opening for doors, windows, electrical conduits, switch boards etc., including providing with two coats of approved steel primer etc. complete, all as per direction of Engineer-in-charge
- Item number
- 9.154
- Analysis basis
- Details of cost for 2.4x2.4 m panel=5.76m
- Priced inputs
- 8
- Derived rate
- ₹166.80 / kg
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.154 — Providing and fixing frame work for partitions/ wall lining etc. made of 50x50x1.6 mm hollow MS tube, placed along the walls, ceiling and floor in a grid pattern with spacing @ 60 cm centre to centre both ways (vertically & horizontally) or at required spacing near opening, with necessary welding at junctions and fixing the frame to wall/ ceiling/ floors with steel dash fasteners of 8 mm dia, 75 mm long bolt, including making provision for opening for doors, windows, electrical conduits, switch boards etc., including providing with two coats of approved steel primer etc. complete, all as per direction of Engineer-in-charge — is derived from 8 priced inputs for 2.4x2.4 m and works out to ₹166.80 per kg after water charges, GST, CPOH and cess. The full build-up is below.
- or 58.35 Kg
- MATERIAL ²
- M.S.Pipe section @ 10.13 kg/sqm=58.35 Kg+
- Total = 61.27 Kg
- Steel primer
- 5 x 2 x 2.40 x 0.05 x 4 = 4.80 sqm
- Add 5% wastage = 2.92 Kg
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 4009 | Mild steel tubes hot finished welded typeMaterial | kilogram | 61.27 | 72.00 | 4,411.44 |
| 8776 | Stainless steel dash fastener of 8 mm dia and 75 mm long boltMaterial | each | 20 | 19.00 | 380.00 |
| Rate as per Item No.13.50.3 of SH:FINISHINGRate as per item 13.50.3Sub-analysis | sqm | 4.8 | 67.40 | 323.52 | |
| 0116 | Fitter (grade 1)Labour | day | 0.4 | 897.00 | 358.80 |
| 0103 | Blacksmith 2nd classLabour | day | 0.53 | 816.00 | 432.48 |
| 0114 | BeldarLabour | day | 1.23 | 736.00 | 905.28 |
| 0100 | BandhaniLabour | day | 0.06 | 816.00 | 48.96 |
| 9999 | SundriesMaterial | L.S. | 33.56 | 2.27 | 76.18 |
- TOTAL
- 6,936.66
- Add 1 % Water charges on “W-A”
- 66.13
- TOTAL
- 7,002.79
- Add GST on “X-A” (multiplying factor 0.2127)
- 1,420.68
- TOTAL
- 8,423.47
- Add 15% CPOH on “Y-A”
- 1,214.99
- TOTAL
- 9,638.46
- Add Cess @ 1% on “Z-A”
- 93.15
- Cost of 58.35 kg
- 9,731.61
- Cost of 1 kg
- 166.78
- Say
- 166.80
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 693. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.