Skip to main content
R/DAR 2023

Providing and fixing frame work for partitions/ wall lining etc. made of 50x50x1.6 mm hollow MS tube, placed along the walls, ceiling and floor in a grid pattern with spacing @ 60 cm centre to centre both ways (vertically & horizontally) or at required spacing near opening, with necessary welding at junctions and fixing the frame to wall/ ceiling/ floors with steel dash fasteners of 8 mm dia, 75 mm long bolt, including making provision for opening for doors, windows, electrical conduits, switch boards etc., including providing with two coats of approved steel primer etc. complete, all as per direction of Engineer-in-charge

Item number
9.154
Analysis basis
2.4x2.4 m
Priced inputs
8
Derived rate
₹166.80/ KG
D-01/RATE ANALYSISITEM 9.154

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.154 (Providing and fixing frame work for partitions/ wall lining etc. made of 50x50x1.6 mm hollow MS tube, placed along the walls, ceiling and floor in a grid pattern with spacing @ 60 cm centre to centre both ways (vertically & horizontally) or at required spacing near opening, with necessary welding at junctions and fixing the frame to wall/ ceiling/ floors with steel dash fasteners of 8 mm dia, 75 mm long bolt, including making provision for opening for doors, windows, electrical conduits, switch boards etc., including providing with two coats of approved steel primer etc. complete, all as per direction of Engineer-in-charge) is derived from 8 priced inputs for 2.4x2.4 m and works out to ₹166.80 per kg after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • or 58.35 Kg
  • MATERIAL ²
  • M.S.Pipe section @ 10.13 kg/sqm=58.35 Kg+
  • Total = 61.27 Kg
  • Steel primer
  • 5 x 2 x 2.40 x 0.05 x 4 = 4.80 sqm
  • Add 5% wastage = 2.92 Kg
ANALYSIS OF RATES · ITEM 9.154DETAILS OF COST FOR 2.4X2.4 M PANEL=5.76M
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
4009MATMild steel tubes hot finished welded typekilogram61.2772.004,411.44
8776MATStainless steel dash fastener of 8 mm dia and 75 mm long bolteach2019.00380.00
SUBRate as per Item No.13.50.3 of SH:FINISHINGRate as per item 13.50.3sqm4.867.40323.52
0116LABFitter (grade 1)day0.4897.00358.80
0103LABBlacksmith 2nd classday0.53816.00432.48
0114LABBeldarday1.23736.00905.28
0100LABBandhaniday0.06816.0048.96
9999MATSundriesL.S.33.562.2776.18
BUILD-UP TO RATE
TOTAL
6,936.66
Add 1 % Water charges on “W-A”
+66.13
TOTAL
7,002.79
Add GST on “X-A” (multiplying factor 0.2127)
+1,420.68
TOTAL
8,423.47
Add 15% CPOH on “Y-A”
+1,214.99
TOTAL
9,638.46
Add Cess @ 1% on “Z-A”
+93.15
Cost of 58.35 kg
9,731.61
Cost of 1 kg
166.78
SAY
₹166.80
D-02/SOURCEPRINTED PAGE 693
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
693

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 693. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.