Providing and fixing steel (white power coated) crescent lock for uPVC sliding window/ door with necessary screws etc. complete

Item number
9.153
Analysis basis
10 Nos
Priced inputs
4
Derived rate
₹198.30/ NO
D-01/RATE ANALYSISITEM 9.153

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.153 (Providing and fixing steel (white power coated) crescent lock for uPVC sliding window/ door with necessary screws etc. complete) is derived from 4 priced inputs for 10 Nos and works out to ₹198.30 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.153DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8754MATZinc alloy (white powder coated) casement lock for uPVC windowsZinc alloy (white powder coated) cresent lock for uPVC sliding door/ windoweach10127.001,270.00
9977MATCarriage of materialsL.S.4.422.2710.03
9999MATSundries(Screws)L.S.32.276.81
0156LABCarpenter (average)day0.125857.00107.13
BUILD-UP TO RATE
TOTAL
1,393.97
Add 1 % Water charges on “W”
+13.94
TOTAL
1,407.91
Add GST on “X” (multiplying factor 0.2127)
+299.46
TOTAL
1,707.37
Add 15% CPOH on “Y”
+256.11
TOTAL
1,963.48
Add Cess @ 1% on “Z”
+19.63
Cost of 10 Nos
1,983.11
Cost of 1 No
198.31
SAY
₹198.30
D-02/SOURCEPRINTED PAGE 692
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
692

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 692. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.