Providing and fixing steel roller for uPVC sliding door with necessary screws etc. complete
- Item number
- 9.152
- Analysis basis
- 10 Nos
- Priced inputs
- 4
- Derived rate
- ₹185.50/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.152 (Providing and fixing steel roller for uPVC sliding door with necessary screws etc. complete) is derived from 4 priced inputs for 10 Nos and works out to ₹185.50 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8753 | MAT | Zinc alloy rollers for uPVC doorStainless Steel (SS - 304) with adjustable double nylon roller (weight bearing capacity to be 120 Kg) for uPVC sliding door/window | each | 10 | 118.00 | 1,180.00 |
| 9977 | MAT | Carriage of materials | L.S. | 4.42 | 2.27 | 10.03 |
| 9999 | MAT | Sundries(Screws) | L.S. | 3 | 2.27 | 6.81 |
| 0156 | LAB | Carpenter (average) | day | 0.125 | 857.00 | 107.13 |
- TOTAL
- 1,303.97
- Add 1 % Water charges on “W”
- +13.04
- TOTAL
- 1,317.01
- Add GST on “X” (multiplying factor 0.2127)
- +280.13
- TOTAL
- 1,597.14
- Add 15% CPOH on “Y”
- +239.57
- TOTAL
- 1,836.71
- Add Cess @ 1% on “Z”
- +18.37
- Cost of 10 Nos
- 1,855.08
- Cost of 1 No
- 185.51
- SAY
- ₹185.50
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 692
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 692. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate