Providing and fixing steel roller for uPVC sliding window with necessary screws etc. complete
- Item number
- 9.151
- Analysis basis
- 10 Nos
- Priced inputs
- 4
- Derived rate
- ₹115.80/ NO
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.151 (Providing and fixing steel roller for uPVC sliding window with necessary screws etc. complete) is derived from 4 priced inputs for 10 Nos and works out to ₹115.80 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8752 | MAT | Zinc alloy rollers for uPVC windowsZinc alloy/ SS 304 body with single nylon roller (weight bearing capacity to be 40 Kg) for uPVC sliding window | each | 10 | 69.00 | 690.00 |
| 9977 | MAT | Carriage of materials | L.S. | 4.42 | 2.27 | 10.03 |
| 9999 | MAT | Sundries(Screws) | L.S. | 3 | 2.27 | 6.81 |
| 0156 | LAB | Carpenter (average) | day | 0.125 | 857.00 | 107.13 |
- TOTAL
- 813.97
- Add 1 % Water charges on “W”
- +8.14
- TOTAL
- 822.11
- Add GST on “X” (multiplying factor 0.2127)
- +174.86
- TOTAL
- 996.97
- Add 15% CPOH on “Y”
- +149.55
- TOTAL
- 1,146.52
- Add Cess @ 1% on “Z”
- +11.47
- Cost of 10 Nos
- 1,157.99
- Cost of 1 No
- 115.80
- SAY
- ₹115.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 691
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 691. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.