Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked M.S. pressed butt hinges bright finished of required size with necessary screws

For 2nd class teak wood and other class of wood shutters

Item number
9.15.2.1
Analysis basis
Details of cost of hinges with screws for
Priced inputs
4
Derived rate
59.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.15.2.1 Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked M.S. pressed butt hinges bright finished of required size with necessary screws For 2nd class teak wood and other class of wood shutters — is derived from 4 priced inputs and works out to ₹59.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • shutters of size 200x108cm = 2.16 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
0595Bright finished or black enamelled ISI marked IS: 1341 mild steel pressed butt hinges 100x58x1.90 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 100x58x 1.90 mmMaterial10 Nos0.680.0048.00
0597Bright finished or black enamelled ISI marked IS: 1341 mild steel steel butt hinges50x37x1.50 mmBright finished or black enameled ISI marked IS:1341 mild steel pressed butt hinges 50x37x 1.50 mmMaterial10 Nos0.249.009.80
0637Bright finished or black enamelled mild steel screws 40 mmBright finished or black enameled mild steel screws 40 mmMaterial100 Nos0.4862.0029.76
0640Bright finished or black enamelled mild steel screws 20 mmBright finished or black enameled mild steel screws 20 mmMaterial100 Nos0.0840.003.20
TOTAL
90.76
Add 1 % Water charges on “W”
0.91
TOTAL
91.67
Add GST on “X” (multiplying factor 0.2127)
19.50
TOTAL
111.17
Add 15% CPOH on “Y”
16.68
TOTAL
127.85
Add Cess @ 1% on “Z”
1.28
Cost of 2.16 sqm.
129.13
Cost of 1 sqm.
59.78
Say
59.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 465. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.