Skip to main content
R/DAR 2023

Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked Stainless steel butt hinges with stainless steel screws

For 2nd class teak wood and other class of wood shutters
Item number
9.15.1.1
Analysis basis
shutter of
Priced inputs
4
Derived rate
₹253.30/ SQM
D-01/RATE ANALYSISITEM 9.15.1.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.15.1.1 (Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked Stainless steel butt hinges with stainless steel screws : For 2nd class teak wood and other class of wood shutters) is derived from 4 priced inputs for shutter of and works out to ₹253.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 200x108cm = 2.16 sqm.
ANALYSIS OF RATES · ITEM 9.15.1.1DETAILS OF COST OF FITTINGS FOR SHUTTER OF SIZE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8220MATStainless steel butt hinges (heavy weight) 100x60x2.5 mm IS : 12817 markedStainless steel butt hinges (heavy weight) 100x60x2.5 mm IS :12817 marked10 Nos0.6345.00207.00
8218MATStainless steel butt hinges 50x37x1.5 mm IS : 12817 marked10 Nos0.2170.0034.00
8211MATStainless steel screws 40 mm100 Nos0.48270.00129.60
8214MATStainless steel screws 20 mm100 Nos0.08175.0014.00
BUILD-UP TO RATE
TOTAL
384.60
Add 1 % Water charges on “W”
+3.85
TOTAL
388.45
Add GST on “X” (multiplying factor 0.2127)
+82.62
TOTAL
471.07
Add 15% CPOH on “Y”
+70.66
TOTAL
541.73
Add Cess @ 1% on “Z”
+5.42
Cost of 2.16 sqm.
547.15
Cost of 1 sqm.
253.31
SAY
₹253.30
D-02/SOURCEPRINTED PAGE 465
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
465

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 465. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.