Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked Stainless steel butt hinges with stainless steel screws
- Item number
- 9.15.1.1
- Analysis basis
- shutter of
- Priced inputs
- 4
- Derived rate
- ₹253.30/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.15.1.1 (Deduct for not providing hinges in doors, windows or clerestory window shutters with : ISI marked Stainless steel butt hinges with stainless steel screws : For 2nd class teak wood and other class of wood shutters) is derived from 4 priced inputs for shutter of and works out to ₹253.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 200x108cm = 2.16 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8220 | MAT | Stainless steel butt hinges (heavy weight) 100x60x2.5 mm IS : 12817 markedStainless steel butt hinges (heavy weight) 100x60x2.5 mm IS :12817 marked | 10 Nos | 0.6 | 345.00 | 207.00 |
| 8218 | MAT | Stainless steel butt hinges 50x37x1.5 mm IS : 12817 marked | 10 Nos | 0.2 | 170.00 | 34.00 |
| 8211 | MAT | Stainless steel screws 40 mm | 100 Nos | 0.48 | 270.00 | 129.60 |
| 8214 | MAT | Stainless steel screws 20 mm | 100 Nos | 0.08 | 175.00 | 14.00 |
- TOTAL
- 384.60
- Add 1 % Water charges on “W”
- +3.85
- TOTAL
- 388.45
- Add GST on “X” (multiplying factor 0.2127)
- +82.62
- TOTAL
- 471.07
- Add 15% CPOH on “Y”
- +70.66
- TOTAL
- 541.73
- Add Cess @ 1% on “Z”
- +5.42
- Cost of 2.16 sqm.
- 547.15
- Cost of 1 sqm.
- 253.31
- SAY
- ₹253.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 465
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 465. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.