CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing fire resistant door frame of section 143 x 57 mm having built in rebate made out of 16 SWG G.I. sheet (zinc coating not less than 120 gm/sqm) duly filled with vermuculite based concrete mix, suitable for mounting 60 minutes fire rated door shutters. The frame is fitted with intumuscent fire seal strip of size 10x4 mm (minimum) alround the frame and fixing with dash fastener of approved size and make, including applying a coat of approved brand fire resistant primer etc. complete as per direction of Engineer-in-charge (Dash fastener to be paid for separately)
- Item number
- 9.136
- Analysis basis
- Details of cost for 3300/2750mm Door (9.10
- Priced inputs
- 3
- Derived rate
- ₹1,709.25 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.136 — Providing and fixing fire resistant door frame of section 143 x 57 mm having built in rebate made out of 16 SWG G.I. sheet (zinc coating not less than 120 gm/sqm) duly filled with vermuculite based concrete mix, suitable for mounting 60 minutes fire rated door shutters. The frame is fitted with intumuscent fire seal strip of size 10x4 mm (minimum) alround the frame and fixing with dash fastener of approved size and make, including applying a coat of approved brand fire resistant primer etc. complete as per direction of Engineer-in-charge (Dash fastener to be paid for separately) — is derived from 3 priced inputs and works out to ₹1,709.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- metre length)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8738 | Factory made door frame fire rated ( 60 minutes) made with 16 SWG G.I. Sheet of section 143 mm x 57 mm duly filled with vermuculite based concrete mixFactory made door frame fire rated (60 minutes) made with 16 SWG G.I. Sheet of section 143 mm x 57 mm duly filled with vermuculite based concrete mixMaterial | metre | 9.1 | 1,168.00 | 10,628.80 |
| 9999 | Labour for fixingMaterial | L.S. | 130 | 2.27 | 295.10 |
| 9988 | Sundries and carriageMaterial | L.S. | 4.23 | 2.27 | 9.60 |
- TOTAL
- 10,933.50
- Add 1 % Water charges on “W”
- 109.34
- TOTAL
- 11,042.84
- Add GST on “X” (multiplying factor 0.2127)
- 2,348.81
- TOTAL
- 13,391.65
- Add 15% CPOH on “Y”
- 2,008.75
- TOTAL
- 15,400.40
- Add Cess @ 1% on “Z”
- 154.00
- Cost of 9.10 metres
- 15,554.40
- Cost of 1.00 metre
- 1,709.27
- Say
- 1,709.25
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 619. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.