Providing and fixing fire resistant door frame of section 143 x 57 mm having built in rebate made out of 16 SWG G.I. sheet (zinc coating not less than 120 gm/sqm) duly filled with vermuculite based concrete mix, suitable for mounting 60 minutes fire rated door shutters. The frame is fitted with intumuscent fire seal strip of size 10x4 mm (minimum) alround the frame and fixing with dash fastener of approved size and make, including applying a coat of approved brand fire resistant primer etc. complete as per direction of Engineer-in-charge (Dash fastener to be paid for separately)

Item number
9.136
Analysis basis
Details of cost for 3300/2750mm Door (9.10
Priced inputs
3
Derived rate
₹1,709.25/ METRE
D-01/RATE ANALYSISITEM 9.136

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.136 (Providing and fixing fire resistant door frame of section 143 x 57 mm having built in rebate made out of 16 SWG G.I. sheet (zinc coating not less than 120 gm/sqm) duly filled with vermuculite based concrete mix, suitable for mounting 60 minutes fire rated door shutters. The frame is fitted with intumuscent fire seal strip of size 10x4 mm (minimum) alround the frame and fixing with dash fastener of approved size and make, including applying a coat of approved brand fire resistant primer etc. complete as per direction of Engineer-in-charge (Dash fastener to be paid for separately)) is derived from 3 priced inputs and works out to ₹1,709.25 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • metre length)
ANALYSIS OF RATES · ITEM 9.136DETAILS OF COST FOR 3300/2750MM DOOR (9.10
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8738MATFactory made door frame fire rated ( 60 minutes) made with 16 SWG G.I. Sheet of section 143 mm x 57 mm duly filled with vermuculite based concrete mixFactory made door frame fire rated (60 minutes) made with 16 SWG G.I. Sheet of section 143 mm x 57 mm duly filled with vermuculite based concrete mixmetre9.11,168.0010,628.80
9999MATLabour for fixingL.S.1302.27295.10
9988MATSundries and carriageL.S.4.232.279.60
BUILD-UP TO RATE
TOTAL
10,933.50
Add 1 % Water charges on “W”
+109.34
TOTAL
11,042.84
Add GST on “X” (multiplying factor 0.2127)
+2,348.81
TOTAL
13,391.65
Add 15% CPOH on “Y”
+2,008.75
TOTAL
15,400.40
Add Cess @ 1% on “Z”
+154.00
Cost of 9.10 metres
15,554.40
Cost of 1.00 metre
1,709.27
SAY
₹1,709.25
D-02/SOURCEPRINTED PAGE 619
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
619

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 619. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.