Providing and fixing 50 mm thick glazed fire resistant door shutters of 60 minutes fire rating conforming to IS:3614 (Part-II), tested and certified as per laboratory approved by Engineer-incharge, with suitable mounting on door frame, consisting of vertical styles, lock rail, top rail 100 mm wide, bottom rail 200 mm wide, made out of 16 SWG G.I.sheet (zinc coating not less than 120 gm/sqm) duly filled FR insulation material and fixing with necessary stainless steel ball bearing hinges of approved make, including applying a coat of approved fire resistant primer etc. all complete as per direction of Engineer-in-charge (panneling to be paid for separately)

Item number
9.137
Analysis basis
Details of cost for 3.50 sqm (Door size-
Priced inputs
3
Derived rate
7,533.20 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.137 Providing and fixing 50 mm thick glazed fire resistant door shutters of 60 minutes fire rating conforming to IS:3614 (Part-II), tested and certified as per laboratory approved by Engineer-incharge, with suitable mounting on door frame, consisting of vertical styles, lock rail, top rail 100 mm wide, bottom rail 200 mm wide, made out of 16 SWG G.I.sheet (zinc coating not less than 120 gm/sqm) duly filled FR insulation material and fixing with necessary stainless steel ball bearing hinges of approved make, including applying a coat of approved fire resistant primer etc. all complete as per direction of Engineer-in-charge (panneling to be paid for separately) — is derived from 3 priced inputs for 3.50 sqm and works out to ₹7,533.20 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 1710x2050 mm)
CodeInputUnitQuantityRate (INR)Amount (INR)
8739Fire rated door shutter made with 16 SWG G.I. sheet( 60 minutes) without panelFire rated door shutter made with 16 SWG G.I. sheet (60 minutes) without panelMaterialsqm3.55,172.0018,102.00
9999Labour for fixingMaterialL.S.1802.27408.60
9988Sundries & CarriageMaterialL.S.102.2722.70
TOTAL
18,533.30
Add 1 % Water charges on “W”
185.33
TOTAL
18,718.63
Add GST on “X” (multiplying factor 0.2127)
3,981.45
TOTAL
22,700.08
Add 15% CPOH on “Y”
3,405.01
TOTAL
26,105.09
Add Cess @ 1% on “Z”
261.05
Cost of 3.50 sqm
26,366.14
Cost of 1 sqm
7,533.18
Say
7,533.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 620. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works