Providing and fixing cup board shutters with 25 mm thick veneered particle board IS : 3097 marked, exterior grade (Grade I), of approved make, including IInd class teak wood lipping of 25 mm wide x 12 mm thick with necessary screws and bright finished stainless steel piano hinges, complete as per direction of Engineer-in-Charge
- Item number
- 9.130.2
- Analysis basis
- one shutter
- Priced inputs
- 9
- Derived rate
- ₹1,809.40/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.130.2 (Providing and fixing cup board shutters with 25 mm thick veneered particle board IS : 3097 marked, exterior grade (Grade I), of approved make, including IInd class teak wood lipping of 25 mm wide x 12 mm thick with necessary screws and bright finished stainless steel piano hinges, complete as per direction of Engineer-in-Charge With non decorative veneering on both sides) is derived from 9 priced inputs for one shutter and works out to ₹1,809.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 2.20sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 7269 | MAT | 25 mm thick particle board | sqm | 2.2 | 450.00 | 990.00 |
| 0347 | MAT | Extra for veneered particle board with Commercial veneering on both sides | sqm | 2.2 | 170.00 | 374.00 |
| 9977 | MAT | CARRIAGE | L.S. | 29.64 | 2.27 | 67.28 |
| 8678 | MAT | 1mm thick 35mm wide bright finished stainless steel piano hinges1 mm thick 35 mm wide bright finished stainless steel piano hinges | metre | 4.4 | 52.00 | 228.80 |
| 0685 | MAT | Oxidised mild steel screws 25 mm | 100 Nos | 1.25 | 39.00 | 48.75 |
| 0111 | LAB | Carpenter 1st class | day | 0.5 | 897.00 | 448.50 |
| 0114 | LAB | Beldar | day | 0.5 | 736.00 | 368.00 |
| 0130 | LAB | Mistry | day | 0.07 | 897.00 | 62.79 |
| 7271 | MAT | IInd class teak wood lipping 25 mm wide x 12 mm thickSecond class teak wood lipping 25 mm wide x 12 mm thick | metre | 7 | 30.00 | 210.00 |
- TOTAL
- 2,798.12
- Add 1 % Water charges on “W”
- +27.98
- TOTAL
- 2,826.10
- Add GST on “X” (multiplying factor 0.2127)
- +601.11
- TOTAL
- 3,427.21
- Add 15% CPOH on “Y”
- +514.08
- TOTAL
- 3,941.29
- Add Cess @ 1% on “Z”
- +39.41
- Cost for 2.20sqm.
- 3,980.70
- Cost of 1 sqm
- 1,809.41
- SAY
- ₹1,809.40
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 602
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 602. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.