CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer’s specification and direction of Engineerincharge
Extruded section profile size 42x50 mm
- Item number
- 9.117.2
- Analysis basis
- Detail of cost for 5 metre
- Priced inputs
- 4
- Derived rate
- ₹331.35 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.117.2 — Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer’s specification and direction of Engineerincharge Extruded section profile size 42x50 mm — is derived from 4 priced inputs for 5 metre and works out to ₹331.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8705 | 50mmX42mmX2mm thick Factory made door frame of PVC extruded sections in white, grey or wooden finish50 mmX42 mmX2 mm thick Factory made door frame of PVC extruded sections in white, grey or wooden finishMaterial | metre | 5 | 183.00 | 915.00 |
| 0156 | Carpenter (average)Labour | day | 0.15 | 857.00 | 128.55 |
| 0114 | BeldarLabour | day | 0.15 | 736.00 | 110.40 |
| 9999 | SundriesMaterial | L.S. | 4.68 | 2.27 | 10.62 |
- TOTAL
- 1,164.57
- Add 1 % Water charges on “W”
- 11.65
- TOTAL
- 1,176.22
- Add GST on “X” (multiplying factor 0.2127)
- 250.18
- TOTAL
- 1,426.40
- Add 15% CPOH on “Y”
- 213.96
- TOTAL
- 1,640.36
- Add Cess @ 1% on “Z”
- 16.40
- Cost of 5 metre
- 1,656.76
- Cost for 1 metre
- 331.35
- Say
- 331.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 588. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works