Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer’s specification and direction of Engineerincharge

Extruded section profile size 48x40 mm

Item number
9.117.1
Analysis basis
Detail of cost for 5 metre
Priced inputs
4
Derived rate
270.20 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.117.1 Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the door frame to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the frames reinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the frame complete as per manufacturer’s specification and direction of Engineerincharge Extruded section profile size 48x40 mm — is derived from 4 priced inputs for 5 metre and works out to ₹270.20 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
801048mmX40mmX1.5mm thick Factory made door frame of PVC extruded sections in white, grey or wooden finish48 mmX40 mmX1.5 mm thick Factory made door frame of PVC extruded sections in white, grey or wooden finishMaterialmetre5140.00700.00
0156Carpenter (average)Labourday0.15857.00128.55
0114BeldarLabourday0.15736.00110.40
9999SundriesMaterialL.S.4.682.2710.62
TOTAL
949.57
Add 1 % Water charges on “W”
9.50
TOTAL
959.07
Add GST on “X” (multiplying factor 0.2127)
203.99
TOTAL
1,163.06
Add 15% CPOH on “Y”
174.46
TOTAL
1,337.52
Add Cess @ 1% on “Z”
13.38
Cost of 5 metre
1,350.90
Cost for 1 metre
270.18
Say
270.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 587. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.