Providing and fixing to existing door frames

24 mm thick factory made PVC door shutters made of styles and rails of a uPVC hollow section of size 59x24 mm and wall thickness 2 mm (± 0.2 mm) with inbuilt edging on both sides. The styles and rails mitred and joint at the corners by means of M.S. galvanised/ plastic brackets of size 75x220 mm having wall thickness 1.0 mm and stainless steel screws. The styles of the shutter reinforced by inserting galvanised M.S. tube of size 20x20 mm and 1 mm (± 0.1 mm) wall thickness. The lock rail made up of ‘H’ section, a uPVC hollow section of size 100x24 mm and 2 mm (± 0.2 mm) wall thickness, fixed to the shutter styles by means of plastic/galvanised M.S. ‘U’ cleats. The shutter frame filled with a uPVC multi-chambered single panel of size not less than 620 mm, having over all thickness of 20 mm and 1 mm (± 0.1 mm) wall thickness. The panels filled vertically and tie bar at two places by inserting horizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, complete as per manufacturer’s specification and direction of Engineer-in-charge. (For W.C. and bathroom door shutter)
Item number
9.118.1
Analysis basis
one door
Priced inputs
4
Derived rate
₹2,969.25/ SQM
D-01/RATE ANALYSISITEM 9.118.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.118.1 (Providing and fixing to existing door frames 24 mm thick factory made PVC door shutters made of styles and rails of a uPVC hollow section of size 59x24 mm and wall thickness 2 mm (± 0.2 mm) with inbuilt edging on both sides. The styles and rails mitred and joint at the corners by means of M.S. galvanised/ plastic brackets of size 75x220 mm having wall thickness 1.0 mm and stainless steel screws. The styles of the shutter reinforced by inserting galvanised M.S. tube of size 20x20 mm and 1 mm (± 0.1 mm) wall thickness. The lock rail made up of ‘H’ section, a uPVC hollow section of size 100x24 mm and 2 mm (± 0.2 mm) wall thickness, fixed to the shutter styles by means of plastic/galvanised M.S. ‘U’ cleats. The shutter frame filled with a uPVC multi-chambered single panel of size not less than 620 mm, having over all thickness of 20 mm and 1 mm (± 0.1 mm) wall thickness. The panels filled vertically and tie bar at two places by inserting horizontally 6 mm galvanised M.S. rod and fastened with nuts and washers, complete as per manufacturer’s specification and direction of Engineer-in-charge. (For W.C. and bathroom door shutter)) is derived from 4 priced inputs for one door and works out to ₹2,969.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 2.38 sqm
ANALYSIS OF RATES · ITEM 9.118.1DETAIL OF COST FOR ONE DOOR SHUTTER 2.20X1.08M =
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8001MAT24 mm thick Factory made shutters with frame, rails and panels of PVC extruded sections in white, grey or wooden finish24 mm thick Factory made shutters with style, rails and panels of PVC extruded sections in white, grey or wooden finishsqm2.381,800.004,284.00
0156LABCarpenter (average)day0.4857.00342.80
0114LABBeldarday0.4736.00294.40
9999MATSundriesL.S.20.362.2746.22
BUILD-UP TO RATE
TOTAL
4,967.42
Add 1 % Water charges on “W”
+49.67
TOTAL
5,017.09
Add GST on “X” (multiplying factor 0.2127)
+1,067.14
TOTAL
6,084.23
Add 15% CPOH on “Y”
+912.63
TOTAL
6,996.86
Add Cess @ 1% on “Z”
+69.97
Cost of 2.38 sqm
7,066.83
Cost of 1 sqm
2,969.26
SAY
₹2,969.25
D-02/SOURCEPRINTED PAGE 588
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
588

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 588. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.