Providing and fixing powder coated telescopic drawer channels 300 mm long with necessary screws etc. complete as per directions of Engineerin-charge

Item number
9.115
Analysis basis
10 sets
Priced inputs
3
Derived rate
₹414.20/ SETS
D-01/RATE ANALYSISITEM 9.115

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.115 (Providing and fixing powder coated telescopic drawer channels 300 mm long with necessary screws etc. complete as per directions of Engineerin-charge) is derived from 3 priced inputs for 10 sets and works out to ₹414.20 per sets after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.115DETAILS OF COST FOR 10 SETS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8703MATTelescopic drawer channels 300mm long .Telescopic drawer channels 300 mm longset10264.002,640.00
9977MATCARRIAGEL.S.19.52.2744.27
9999MATSundries including screws and fixing chargesL.S.100.12.27227.23
BUILD-UP TO RATE
TOTAL
2,911.50
Add 1 % Water charges on “W”
+29.12
TOTAL
2,940.62
Add GST on “X” (multiplying factor 0.2127)
+625.47
TOTAL
3,566.09
Add 15% CPOH on “Y”
+534.91
TOTAL
4,101.00
Add Cess @ 1% on “Z”
+41.01
Cost for 10 sets
4,142.01
Cost for 1 set
414.20
SAY
₹414.20
D-02/SOURCEPRINTED PAGE 586
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
586

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 586. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSWOOD AND PVC WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.