CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing Bamboo jaffery/ fencing consisting of superior quality 25mm dia (Average) half cut bamboo placed vertically and fixed together with three numbers horizontal running members of hollock wood in scantling of section 50X25 mm, fixed with nails and G.I wire on existing support complete as per direction of Engineer-in-charge

Item number
9.110
Analysis basis
Details of cost for a bamboo jaffery of size
Priced inputs
7
Derived rate
689.40 / a bamboo

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.110 Providing and fixing Bamboo jaffery/ fencing consisting of superior quality 25mm dia (Average) half cut bamboo placed vertically and fixed together with three numbers horizontal running members of hollock wood in scantling of section 50X25 mm, fixed with nails and G.I wire on existing support complete as per direction of Engineer-in-charge — is derived from 7 priced inputs for a bamboo and works out to ₹689.40 per a bamboo after water charges, GST, CPOH and cess. The full build-up is below.

  • 1.00m x 2.10m = 2.10 sqm
  • Bamboo 25mm of 100/ 2.50 = 40 nos
  • Half cut off = 40/2 .=20 nos. x 2.10 = 42.00m
  • Total = 48.30m
  • Rate of Bamboo 25 mm dia 2.5 metre long
  • for one score i.e. 20nos is Rs. 192
  • for 48.30m qty 48.30 /( 2.5 x 20) = 0.966
  • 3 nos. (1.00 x 0.05 x 0.05) = 0.00375 cum
  • Total = 0.00394 cum or 3.94 cudm
  • Add wastage @ 15% = 6.30 m
  • Add wastage @ 5% = 0.00019 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0305Bamboo 25 mm dia 2.5 metre longMaterialscore0.966420.00405.72
9977Carriage of BambooMaterialL.S.4.832.2710.96
2466Hollock wood in scantlingMaterial10 cudm0.394366.00144.20
9999Nails and wireMaterialL.S.20.252.2745.97
0112Carpenter 2nd classLabourday0.25816.00204.00
0114BeldarLabourday0.25736.00184.00
9999SundriesMaterialL.S.10.052.2722.81
TOTAL
1,017.66
Add 1 % Water charges on “W”
10.18
TOTAL
1,027.84
Add GST on “X” (multiplying factor 0.2127)
218.62
TOTAL
1,246.46
Add 15% CPOH on “Y”
186.97
TOTAL
1,433.43
Add Cess @ 1% on “Z”
14.33
Cost for 2.10 sqm
1,447.76
Cost for 1 sqm
689.41
Say
689.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 583. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.