Providing and fixing PTMT door catcher of length 72 mm and dia. of 42 mm with suitable washers weighing not less than 33 gms

Item number
9.109
Analysis basis
ten Nos
Priced inputs
4
Derived rate
₹40.05/ NO
D-01/RATE ANALYSISITEM 9.109

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.109 (Providing and fixing PTMT door catcher of length 72 mm and dia. of 42 mm with suitable washers weighing not less than 33 gms) is derived from 4 priced inputs for ten Nos and works out to ₹40.05 per no after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 9.109DETAILS OF COST FOR TEN NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7518MATPTMT door catcher 72x42mmPTMT door catcher 72x42 mmeach1024.00240.00
0639MATBright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mm100 Nos0.242.008.40
9977MATCarriage of materialsL.S.2.732.276.20
0111LABCarpenter 1st classday0.03897.0026.91
BUILD-UP TO RATE
TOTAL
281.51
Add 1 % Water charges on “W”
+2.82
TOTAL
284.33
Add GST on “X” (multiplying factor 0.2127)
+60.48
TOTAL
344.81
Add 15% CPOH on “Y”
+51.72
TOTAL
396.53
Add Cess @ 1% on “Z”
+3.97
Cost of 10 Nos
400.50
Cost of 1 No
40.05
SAY
₹40.05
D-02/SOURCEPRINTED PAGE 583
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
583

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 583. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.