Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing PTMT Tower Bolts with 12 mm one piece rod inside and necessary screws etc., complete

202x42x18 mm weighing not less than 78 gms

Item number
9.108.2
Analysis basis
Details of cost for ten Nos.
Priced inputs
4
Derived rate
106.15 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.108.2 Providing and fixing PTMT Tower Bolts with 12 mm one piece rod inside and necessary screws etc., complete 202x42x18 mm weighing not less than 78 gms — is derived from 4 priced inputs for ten Nos and works out to ₹106.15 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7517PTMT Tower bolt 202x42x18mmPTMT Tower bolt 202x42x18 mmMaterialeach1062.00620.00
0638Bright finished or black enamelled mild steel screws 30 mmBright finished or black enameled mild steel screws 30 mmMaterial100 Nos0.848.0038.40
9977Carriage of materialsMaterialL.S.2.732.276.20
0112Carpenter 2nd classLabourday0.1816.0081.60
TOTAL
746.20
Add 1 % Water charges on “W”
7.46
TOTAL
753.66
Add GST on “X” (multiplying factor 0.2127)
160.30
TOTAL
913.96
Add 15% CPOH on “Y”
137.09
TOTAL
1,051.05
Add Cess @ 1% on “Z”
10.51
Cost of 10 Nos
1,061.56
Cost of 1 No
106.16
Say
106.15

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 582. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works