CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing PTMT handles with necessary screws etc. complete

150x34x24 mm weighing not less than 26 gms

Item number
9.106.2
Analysis basis
Details of cost for ten Nos.
Priced inputs
4
Derived rate
41.55 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.106.2 Providing and fixing PTMT handles with necessary screws etc. complete 150x34x24 mm weighing not less than 26 gms — is derived from 4 priced inputs for ten Nos and works out to ₹41.55 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7513PTMT handle 150x34x24mmPTMT handle 150x34x24 mmMaterialeach1022.00220.00
0639Bright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mmMaterial100 Nos0.442.0016.80
9977Carriage of materialsMaterialL.S.2.732.276.20
0112Carpenter 2nd classLabourday0.06816.0048.96
TOTAL
291.96
Add 1 % Water charges on “W”
2.92
TOTAL
294.88
Add GST on “X” (multiplying factor 0.2127)
62.72
TOTAL
357.60
Add 15% CPOH on “Y”
53.64
TOTAL
411.24
Add Cess @ 1% on “Z”
4.11
Cost of 10 Nos
415.35
Cost of 1 No
41.54
Say
41.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 580. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.