CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing PTMT handles with necessary screws etc. complete
125x34x24 mm weighing not less than 23 gms
- Item number
- 9.106.1
- Analysis basis
- Details of cost for ten Nos.
- Priced inputs
- 4
- Derived rate
- ₹42.95 / No
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.106.1 — Providing and fixing PTMT handles with necessary screws etc. complete 125x34x24 mm weighing not less than 23 gms — is derived from 4 priced inputs for ten Nos and works out to ₹42.95 per no after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7512 | PTMT handle 125x34x24mmPTMT handle 125x34x24 mmMaterial | each | 10 | 23.00 | 230.00 |
| 0639 | Bright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mmMaterial | 100 Nos | 0.4 | 42.00 | 16.80 |
| 9977 | Carriage of materialsMaterial | L.S. | 2.73 | 2.27 | 6.20 |
| 0112 | Carpenter 2nd classLabour | day | 0.06 | 816.00 | 48.96 |
- TOTAL
- 301.96
- Add 1 % Water charges on “W”
- 3.02
- TOTAL
- 304.98
- Add GST on “X” (multiplying factor 0.2127)
- 64.87
- TOTAL
- 369.85
- Add 15% CPOH on “Y”
- 55.48
- TOTAL
- 425.33
- Add Cess @ 1% on “Z”
- 4.25
- Cost of 10 Nos
- 429.58
- Cost of 1 No
- 42.96
- Say
- 42.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 580. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works