Skip to main content

CPWD Analysis of Rates · Wood and PVC Work

Providing and fixing PTMT handles with necessary screws etc. complete

125x34x24 mm weighing not less than 23 gms

Item number
9.106.1
Analysis basis
Details of cost for ten Nos.
Priced inputs
4
Derived rate
42.95 / No

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.106.1 Providing and fixing PTMT handles with necessary screws etc. complete 125x34x24 mm weighing not less than 23 gms — is derived from 4 priced inputs for ten Nos and works out to ₹42.95 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
7512PTMT handle 125x34x24mmPTMT handle 125x34x24 mmMaterialeach1023.00230.00
0639Bright finished or black enamelled mild steel screws 25 mmBright finished or black enameled mild steel screws 25 mmMaterial100 Nos0.442.0016.80
9977Carriage of materialsMaterialL.S.2.732.276.20
0112Carpenter 2nd classLabourday0.06816.0048.96
TOTAL
301.96
Add 1 % Water charges on “W”
3.02
TOTAL
304.98
Add GST on “X” (multiplying factor 0.2127)
64.87
TOTAL
369.85
Add 15% CPOH on “Y”
55.48
TOTAL
425.33
Add Cess @ 1% on “Z”
4.25
Cost of 10 Nos
429.58
Cost of 1 No
42.96
Say
42.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 580. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works