CPWD Analysis of Rates · Wood and PVC Work
Providing and fixing partition upto ceiling height consisting of G.I. frame and required board, including providing and fixing of frame work made of special section power pressed/ roll form G.I. sheet with zinc coating of 120 gms/sqm(both side inclusive), consisting of floor and ceiling channel 50mm wide having equal flanges of 32 mm and 0.50 mm thick, fixed to the floor and ceiling at the spacing of 610 mm centre to centre with dash fastener of 12.5 mm dia meter 50 mm length or suitable anchor fastener or metal screws with nylon plugs and the studs 48 mm wide having one flange of 34 mm and other flange 36 mm and 0.50 mm thick fixed vertically within flanges of floor and ceiling channel and placed at a spacing of 610 mm centre to centre by 6 mm dia bolts and nuts, including fixing of studs along both ends of partition fixed flush to wall with suitable anchor fastener or metal screws with nylon plugs at spacing of 450 mm centre to centre, and fixing of boards to both side of frame work by 25 mm long dry wall screws on studs, floor and ceiling channels at the spacing of 300 mm centre to centre. The boards are to be fixed to the frame work with joints staggered to avoid through cracks, M.S. fixing channel of 99 mm width (0.9 mm thick having two flanges of 9.5 mm each) to be provided at the horizontal joints of two boards, fixed to the studs using metal to metal flat head screws, including jointing and finishing to a flush finish with recommended jointing compound, jointing tape, angle beads at corners (25 mm x 25 mm x 0.5 mm), joint finisher and two coats of primer suitable for board as per manufacture’s specification and direction of engineer in charge all complete
66 mm overall thickness partition using 8 mm thick double skin multipurpose cement bonded wood particle board manufactured as per IS: 14276 with suitable cement bonded board screws
- Item number
- 9.105.5
- Analysis basis
- Details of cost for 21.90 sqm
- Priced inputs
- 18
- Derived rate
- ₹2,034.40 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 9.105.5 — Providing and fixing partition upto ceiling height consisting of G.I. frame and required board, including providing and fixing of frame work made of special section power pressed/ roll form G.I. sheet with zinc coating of 120 gms/sqm(both side inclusive), consisting of floor and ceiling channel 50mm wide having equal flanges of 32 mm and 0.50 mm thick, fixed to the floor and ceiling at the spacing of 610 mm centre to centre with dash fastener of 12.5 mm dia meter 50 mm length or suitable anchor fastener or metal screws with nylon plugs and the studs 48 mm wide having one flange of 34 mm and other flange 36 mm and 0.50 mm thick fixed vertically within flanges of floor and ceiling channel and placed at a spacing of 610 mm centre to centre by 6 mm dia bolts and nuts, including fixing of studs along both ends of partition fixed flush to wall with suitable anchor fastener or metal screws with nylon plugs at spacing of 450 mm centre to centre, and fixing of boards to both side of frame work by 25 mm long dry wall screws on studs, floor and ceiling channels at the spacing of 300 mm centre to centre. The boards are to be fixed to the frame work with joints staggered to avoid through cracks, M.S. fixing channel of 99 mm width (0.9 mm thick having two flanges of 9.5 mm each) to be provided at the horizontal joints of two boards, fixed to the studs using metal to metal flat head screws, including jointing and finishing to a flush finish with recommended jointing compound, jointing tape, angle beads at corners (25 mm x 25 mm x 0.5 mm), joint finisher and two coats of primer suitable for board as per manufacture’s specification and direction of engineer in charge all complete 66 mm overall thickness partition using 8 mm thick double skin multipurpose cement bonded wood particle board manufactured as per IS: 14276 with suitable cement bonded board screws — is derived from 18 priced inputs for 21.90 sqm and works out to ₹2,034.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- MATERIAL:
- 2x6.00 =12m
- (6.00/0.61)+1 = 11x3.65 = 40.15m
- [(6.00/0.61)+1]x2=22
- 11x2x2=44 nos=4.40 tens
- Labour for 21.90 sqm.
- 0.3x21.90
- 0.13x21.90
- 0.05x21.90
- 0.35x21.90
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0243 | Multipurpose cement bonded wood particle board 8 mm thick8 mm thick mulitipurpose cement bonded wood particle board conforming to IS : 14276Material | sqm | 43.8 | 230.00 | 10,074.00 |
| 7367 | Galvanised M.S. sheet 0.5 mm thick pressed channel section of size 50x32 mmMaterial | metre | 12 | 65.00 | 780.00 |
| 7369 | Galvanised M.S. sheet 0.50 mm thick pressed stud : 48x34x36 mmMaterial | metre | 40.15 | 76.00 | 3,051.40 |
| 7020 | All drive screws ( for gypsum board) [(3.65/0.30)+1]x11x2 = 308 [(6.00/0.30)+1]x2x2=84 Total = 392All drive screws (for gypsum board)Material | 100 nos | 3.92 | 63.00 | 246.96 |
| 7388 | Dash hold fastener 12.5 mm dia, 50 mm long with 6 mm dia boltMaterial | each | 22 | 10.00 | 220.00 |
| 7048 | Rawl plug 50 mm (designation 10 nos) [(3.65/0.45)+1]x2= 18Rawl plug 50 mm (designation 10)Material | each | 18 | 24.00 | 432.00 |
| 0869 | Plaster of Paris (88/100)x21.9 = 19.27Plaster of ParisMaterial | kg | 19.27 | 7.00 | 134.89 |
| 0763 | Glue (22/100)x21.90=4.82GlueMaterial | kg | 4.82 | 80.00 | 385.60 |
| 7018 | Joint tape roll (120m roll) (300/100)x21.90/120 = 0.584 NoJoint tape rollMaterial | roll | 0.584 | 95.00 | 55.48 |
| 7021 | Primer ( for gypsum board (36/100x21.90 = 7.88 litrePrimer (for gypsum board)Material | litre | 7.88 | 75.00 | 591.00 |
| 1022 | Galvanised steel bolts & nuts 6 mm dia and 25 mm long round head with slotsMaterial | 10 Nos | 4.4 | 38.00 | 167.20 |
| 1211 | G.I. plain washer for seam bolts =0 .44 hundredsG.I. plain washer for seam boltsMaterial | 100 Nos | 0.44 | 32.00 | 14.08 |
| 9999 | Sundries carriageMaterial | L.S | 52 | 2.27 | 118.04 |
| 9999 | Sundries scaffoldingMaterial | L.S | 130 | 2.27 | 295.10 |
| 0111 | Carpenter 1 st classCarpenter 1st classLabour | day | 6.57 | 897.00 | 5,893.29 |
| 0112 | Carpenter 2nd classLabour | day | 2.847 | 816.00 | 2,323.15 |
| 0131 | PainterLabour | day | 1.095 | 816.00 | 893.52 |
| 0114 | BeldarLabour | day | 7.665 | 736.00 | 5,641.44 |
- TOTAL
- 31,317.15
- Add 1 % Water charges on “W”
- 313.17
- TOTAL
- 31,630.32
- Add GST on “X” (multiplying factor 0.2127)
- 6,727.77
- TOTAL
- 38,358.09
- Add 15% CPOH on “Y”
- 5,753.71
- TOTAL
- 44,111.80
- Add Cess @ 1% on “Z”
- 441.12
- Cost of 21.90 sqm
- 44,552.92
- Cost of 1 sqm
- 2,034.38
- Say
- 2,034.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 579. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works